The found and dealt with the defaults of non-synchronous closing in phase-to-phase for 5033 circuit breaker at 500 kV Fanchang station

This text described the East China Power Grid Company and its subordinate companies through carried out the com- missioning of 500 kV transmission system project,found Fanchang 500 kV substation 5033 circuit breaker has non-synchronous closing in phase-to-phase defaults.Technical staff analyzed the recorded waveform with the equipment structural characteristics of wave to determine the reasons for the defaults.The related units eliminates wholeheartedly with the above defaults.
【CateGory Index】: TM561
Download(CAJ format) Download(PDF format)
CAJViewer7.0 supports all the CNKI file formats; AdobeReader only supports the PDF format.
【References】
Chinese Journal Full-text Database 1 Hits
1 ZOU Xiaofeng1,XU Xidong1 ,SHENG Haihua2(1. Zhejiang University,Hangzhou 310027,China; 2. Zhejiang Electric Power Dispatching and Communication Center,Hangzhou 310027,China);Analysis of Electromagnetic Transients of Three-phase Transformer's Non-synchronous Closing and Its Influence on Protection[J];Automation of Electric Power Systems;2009-18
【Co-references】
Chinese Journal Full-text Database 10 Hits
1 LI Jing-yu(Xi′an Jiaotong University,Xi′an 710049,China);Research on DC Bias of Converter Transformer[J];Transformer;2005-09
2 WU Chang-she1,LIN Lin2,LIU Xi-jia2(1.Wenzhou Electric Power Dispatch & Communication Center,Whenzhou 325000,China;2.Wenzhou Electric Power High Voltage Repair & Test Work Area,Whenzhou 325000,China);Inrush current restraint scheme of power transformer differential protection[J];Journal of Electric Power Science and Technology;2009-03
3 Lin Xiangning Liu Shiming Yang Chunming (Huazhong University of Science and Technology 430074 China) Liu Pei(Group of DongFang Electronic Information Industr y Inc 264001 China);Study on Comparisons Among Some Waveform Symmetry Principle Based Transformer Differential Protection[J];Transactions of China Electrotechnical Society;2001-04
4 Yu Baodong Zhang Lizi Yang Yihan(North China Electric Power University) Li Hanqing Li Dianying(Shou Gang Metallurgical Research Insititute);The Transient Magnetizing Model of Core and the Error Computation for CT[J];Transactions of China Electrotechnical Society;1998-06
5 ZHANG Si-jiang, CAO Xiao-long, ZHANG Min-qiang, LI Hong-wei, CHEN Ping (Gansu Tianshui Power Supply Co., Tianshui 741020, China);Handling of Switching off and Switching in Time and Three-phase Un-synchronization for SF_6 Circuit Breaker[J];Electrical Equipment;2007-02
6 HU Jin-song ZHANG Ying-zhen GE Ming XUE Yi-qing (Southwest Electric Power Design Institute, Chengdu 61002l, China);Type selection of Converter Transformer and Its Transportation for UHV Jinping Converter Substation[J];Electrical Equipment;2008-10
7 Whng Zengping;Gao Zhongde; Zhang Ju; Li Ha iying; Wang Tieqiang(North China Electric Power University. 071003. Baoding. China)Liu Zhuo (Harbin Institute of Technology. 150001. Harbin. China);APPLICATION OF FUZZY SET THEORY IN TRANSFORMER PROTECTIONS[J];AUTOMATION OF ELECTRIC POWER SYSTEMS;1998-02
8 Xue Xiangdang', Wen Jianying', Zheng Yunxiang', Ji Chongqing'. YOu Yiming'(1. Tianjin University, Tianjin 300072, China)(2. Textile Engineering College of Tianjin, Tianjin 300160, China);STUDY AND DISCUSSION OF METHODS FOR MITIGATINGAND ELIMINATING GEOMAGNETICALLY INDUCED CURRENT (GIC)[J];AUTOMATION OF ELECTRIC POWER SYSTEMS;2000-07
9 Shi Tiehong,Zhang H ao,L iu Pei Huazhong U niversity of Science and Technology,Wuhan430 0 74,China;OPTIMIZATION OF ACCELERATED TRIP SCHEME BASED ON WAVELET ANALYSIS[J];Automation of Electric Power Systems;2001-02
10 Li Guicun,L iu Wanshun,Jia Qingquan,Cao Fengmei,L i Ying,Deng H uiqiong North China Electric Power U niversity,Beijing10 0 0 85 ,China;A NEW METHOD FOR DETECTING SATURATION OF CURRENT TRANSFORMER BASED ON WAVELET TRANSFORM[J];Automation of Electric Power Systems;2001-05
【Secondary References】
Chinese Journal Full-text Database 1 Hits
1 ZHANG Jia-min1,JIANG Chen2,LI Peng1,YUAN Yu-bo1,ZHANG Jian1(1.Jiangsu Electric Power Company Electric Power Research Institute,Nanjing 211103,China; 2.Jiangsu Frontier Electric Technologies Co.Ltd.,Nanjing 211102,China);Analysis of Converter Transformer Protection Reformation and Research of Testing Technology[J];Jiangsu Electrical Engineering;2013-02
©2006 Tsinghua Tongfang Knowledge Network Technology Co., Ltd.(Beijing)(TTKN) All rights reserved