Analysis of Key Problems of Explosive Demolition for Cofferdam of Water Conveyance Tunnel on Large Hydropower Station

LIU Mei-shan~(1,2),LI Dan~2,PENG Cui-ling~2,ZHANG Song~2(1 University of Science and Technology of China,Hefei 230027,China;2.Yangtze River Scientific Institute,Wuhan 430010,China)  
Besides the safety of protected objects nearby(for example: entrance water tower,strobe etc),the detach stream and flush cinder effect were considered in explosive demolition of cofferdam of water conveyance tunnel on large hydropower station.This paper summarizes and analyzes the key problems and their solving means in cofferdam explosive demolition course for instance of the Xiaowan Hydropower Station.
【CateGory Index】: TV542
Download(CAJ format) Download(PDF format)
CAJViewer7.0 supports all the CNKI file formats; AdobeReader only supports the PDF format.
【References】
Chinese Journal Full-text Database 7 Hits
1 YANG Xin-ku;Geological Team 103,The Bureau of Non-ferrous Geology of Liaoning Province;;Design Points of Fushun Dahuofang Reservoir Water Delivery(Phase Ⅱ) Water Intaking Head Cofferdam Removal Engineering Blasting[J];价值工程;2015-32
2 LIU Hongzhen;Institute of Science and Technology Co. ,Ltd.,China Railway Tunnel Group;;Study on Determination of Unit Consumption of Explosives in Pretreatment of Bedrock/boulders along Alignment of Shield-bored Tunnel without Free Surface[J];隧道建设;2015-03
3 DING Rui1,LU Yaobang2,DANG Rujiao2,LI Yang2(1.China Railway Tunnel Group Co.,Ltd.,Luoyang 471009,Henan,China; 2.Technology Center of China Railway Tunnel Group Co.,Ltd.,Luoyang 471009,Henan,China);Pretreatment of Bedrock Intruding into Shield Tunneling Scope by means of Blasting Hole Drilling from Ground Surface and Blasting Underground[J];隧道建设;2013-03
4 Lu Yaobang1 Liu Hongzhen1 You Yongfeng2 Xu Chaohui2 (1 China Railway Tunnel Group Co., Ltd., Luoyang 471009; 2 China Railway Tunnel Co., Ltd., Zhenzhou 450003);Key Techniques for the Pretreatment of Boulder Blasting in an Under-Sea Shield-Driven Tunnel[J];现代隧道技术;2012-05
5 CHEN Ming,ZHONG Quan,LU Wen-bo,SHU Da-qiang(College of Water Resources and Hydroelecrtic Engineering,Wuhan University,Wuhan 430072,China);Study on Water Flow Impact Residue Technology of Explosive Demolition of Diversion Tunnel Intake Cofferdam[J];爆破;2010-03
6 ZHANG Degao1,2,LI Yanchen2(1.Sichuan University,Chengdu 610065,China;2.Sinohydro Bureau 14 Co.,Ltd.,Kunming 650041,China);Blasting Demolition Technology of Cofferdam at the Entrance and Exit of Right Diversion Tunnel in Jinping Stage I Hydropower Station[J];隧道建设;2009-03
7 ZHANG Li-jie,BIAN Zhi-hua,JING Feng,YANG Jun(Key Laboratory of Geotechnical Mechanics and Engineering of the Ministry of Water Resources,Yangtze River Scientific Research Institute,Wuhan 430010,China);Anchorage Cable Unloading Technology in Cofferdam of Diversion Tunnel Inlet of Some Water Power Station[J];长江科学院院报;2008-05
【Citations】
Chinese Journal Full-text Database 2 Hits
1 GUO Shi ming and TANG Shi lai (Yunnan Dachaoshan Hydropower Company Ltd ) WANG Wen hui and LIU Hua (Changjiang Academy of Sciences) XIA Zhong chun (China Fourteenth Engineering Bureau of Water Resources and Hydropower);Test and study on the blasting removal of the cofferdam in the tailrace mouth of Dachaoshan Hydropower Station[J];水力发电;2001-12
2 ZHANG Wen xuan, ZHANG Zhen yu, FAN Chang yu, XUE Jun bing (Yangtze River Scientific Research Institute, Wuhan, 430010);Explosive Demolition of Cofferdam and Rock-dyke of Water Conveyance Tunnel on Dachaoshan Hydropower Station[J];爆破;2000-S1
【Co-citations】
Chinese Journal Full-text Database 8 Hits
1 CHEN Ming,ZHONG Quan,LU Wen-bo,SHU Da-qiang(College of Water Resources and Hydroelecrtic Engineering,Wuhan University,Wuhan 430072,China);Study on Water Flow Impact Residue Technology of Explosive Demolition of Diversion Tunnel Intake Cofferdam[J];爆破;2010-03
2 ZHANG Wen-xuan~1 LIU Mei-shan~2 (1.University of Science and Technology of China,Hefei 230027,China;2.Key Laboratory of Geotechnical Mechanics and Engineering of Ministry of Water Resources,Wuhan 430010,China);RESEARCH ON SAFETY PROTECTION PROBLEMS IN BLASTING DEMOLITION OF COFFERDAM AND ROCK RIDGE OF LARGE HYDROPOWER STATION[J];工程爆破;2008-04
3 LIU Mei-shan~(1,2),LI Dan~2,PENG Cui-ling~2,ZHANG Song~2(1 University of Science and Technology of China,Hefei 230027,China;2.Yangtze River Scientific Institute,Wuhan 430010,China);Analysis of Key Problems of Explosive Demolition for Cofferdam of Water Conveyance Tunnel on Large Hydropower Station[J];爆破;2006-02
4 LIU Mei-shan~(1,2), ZHANG Zheng-yu~1, LI Yong-chi~2, ZHAO Gen~(1,2)(1. Yangtze River Science Institute,Wuhan 430010, Hubei,China;2.University of Science and Technology of China,Hefei 230027,Anhui,China);BLASTING DEMOLITION OF COFFERDAM INLET OF WATER DIVERSION TUNNEL AT GOUPITAN HYDROPOWER STATION[J];工程爆破;2005-01
5 Liu Mei-shan1, 2,Zhang Zheng-yu1,Shen Si-yuan3,Zhang Wen-xuan1, 2,Zhao Gen1, 2(1. Yangtze River Scientific Institute,Wuhan Hubei 430010;2. University of Science and Technology of China,Hefei Anhui 230027;3. Xiaowan 141 Hydropower Project Unite,Fengqing Yunnan 675909);Explosive demolition of cofferdam and rock-dyke of water conveyance tunnelon of Xiaowan Hydropower Station[J];水力发电;2004-10
6 LIU Mei-shan~(1,2),LI Yong-chi~1,ZHANG Zheng-yu~2,WU Xin-xia~2,ZHANG Wen-xuan~2 (1.University of Science and Technology of China,Hefei 230027,China; 2.Yangtze River Scientific Research Institute,Wuhan 430010,China);BLASTING DEMOLITION OF ROCK-DYKE AT INLET OF NO 2 WATER-DIVERSION TUNNEL IN HONGJIADU HYDROPOWER STATION[J];工程爆破;2004-01
7 YI Chang-ping,XU Hong-tao,LU Wen-bo,SHU Da-qiang Wuhan University ,Hubei Wuhan 430072,China);Influence of riverway on transmission of blasting seismic wave[J];长江科学院院报;2003-S1
8 WANG Fei-yue~1, HUANG Ning~2, Wan Xiao-lin2- (1.The 378 Junction Group at Three Gorges Project, Yichang 443133,China; 2.Investigation and Design Institute of the Yangtze River Water Conservancy Committee, Wuhan 430010, China);Control of influence of blasting vibration on fresh concrete during excavation of right dam foundation at Three Gorges Project[J];长江科学院院报;2003-S1
【Co-references】
Chinese Journal Full-text Database 10 Hits
1 DANG Rujiao(Technology Center of China Railway Tunnel Group Co.,Ltd.,Luoyang 471009,Henan,China);Technology for Geophysical Prospecting of Blasting and Grouting Effects of Bed Rocks[J];隧道建设;2012-05
2 Lu Yaobang1 Liu Hongzhen1 You Yongfeng2 Xu Chaohui2 (1 China Railway Tunnel Group Co., Ltd., Luoyang 471009; 2 China Railway Tunnel Co., Ltd., Zhenzhou 450003);Key Techniques for the Pretreatment of Boulder Blasting in an Under-Sea Shield-Driven Tunnel[J];现代隧道技术;2012-05
3 WANG Penghua(Taishan Nuclear Power Joint Venture Co.,Ltd.,Taishan 529228,Guangdong,China);Treatment of Boulders Encountered in Shield Tunneling under Different Geological Conditions[J];隧道建设;2012-04
4 ZENG Liang1,LI Lu2(1.China Railway Tunnel Survey & Design Institute Co.,Ltd.,Tianjin 300133,China; 2.Shenzhen Metro Group Co.,Ltd.,Shenzhen 518026,Guangdong,China);Application of Deep-hole Loosening Blasting Technology in Shield Tunneling through Long-distance Hard Rocks[J];隧道建设;2012-04
5 HONG Kairong1,LU Yaobang2,LIANG Kuisheng3,LIU Hongzhen2 (1.China Railway Tunnel Group Co.,Ltd.,Luoyang 471009,Henan,China; 2.Technology Center of China Railway Tunnel Group Co.,Ltd.,Luoyang 471009,Henan,China; 3.China Railway Tunnel Stock Co.,Ltd.,Zhengzhou 450003,China);Key Construction Technologies for Arrival of Sea-crossing Slurry Shield before Completion of Arriving Shaft Sinking[J];隧道建设;2012-02
6 Deng Bin1 Gu Xiaofang2(1 Shenzhen Municipal Engineering Corp.,Shenzhen 518000; 2 Shenzhen Water Resources Planning & Design Institute,Shenzhen 518000);Study of Shield Construction Technology in Soft Upper Stratum and Hard Under Stratum[J];现代隧道技术;2012-02
7 Zhu Weibin1 Huang Weiran2 Meng Qingbiao3 Hong Yong3(1 General Construction Department of Guangzhou Metro Corporation,Guangzhou 510380; 2 Guangzhou Mass Transit Engineering Consultant Co.,Ltd.,Guangzhou 510405; 3 Guangdong Blasting Engineering Co.,Ltd.,Guangzhou 510507);Research on Controlled Blasting Technology for Boulders and Invading Bedrock in Shield Construction[J];现代隧道技术;2011-05
8 YU Yong-qiang1,LU Yao-bang1,YANG Xiao-lin2,GAO Fu-qiang2(1.School of Civil Engineering,Henan Polytechnic University,Jiaozuo 454000,Henan,China;2.Department of Civil Engineering,Luoyang Institute of Science and Technology,Luoyang 471000,Henan,China);BLASTING VIBRATION EFFECT ON TUNNEL EXCAVATION WITH HIGH GEOSTRESS AND FRACTURE ZONES[J];工程爆破;2010-03
9 ZHANG Wen-xuan~1 LIU Mei-shan~2 (1.University of Science and Technology of China,Hefei 230027,China;2.Key Laboratory of Geotechnical Mechanics and Engineering of Ministry of Water Resources,Wuhan 430010,China);RESEARCH ON SAFETY PROTECTION PROBLEMS IN BLASTING DEMOLITION OF COFFERDAM AND ROCK RIDGE OF LARGE HYDROPOWER STATION[J];工程爆破;2008-04
10 DUAN Bao-fu(University of Science and Technology,Qingdao 266510,Shandong,China);DISCUSSION AND APPLICATION OF SAFE TECHNOLOGY IN DEMOLITION BLASTING[J];工程爆破;2007-01
【Secondary References】
Chinese Journal Full-text Database 9 Hits
1 LUO Ye-jun;China Railway First Survey and Design Institute Group Co.,Ltd.;;Study of Alignment Plan of Anshun to Ziyun Expressway in Complex Geological Area[J];铁道标准设计;2016-02
2 HONG Kairong;China Railway Tunnel Group Co. ,Ltd.;State Key Laboratory of Shield Machine and Boring Technology;;State-of-art and Prospect of Tunnels and Underground Works in China[J];隧道建设;2015-02
3 Huang Weiran;Zhu Weibin;Liu Renhuai;College of Science and Engineering, Jinan University;Guangzhou Mass Transit Engineering Consultant Co. Ltd.;Guangzhou Metro Corporation;;Risks and Countermeasures for the Shenzhen-Guangzhou-Zhongshan(SGZ)Shield-Tunnel Project Crossing the Pearl River Estuary[J];现代隧道技术;2014-04
4 LU Yaobang;LU Yaoping;LIU Hongzhen;LI Zhiguo;Scientific Research Institutes of China Railway Tunnel Group Co.,Ltd;;Research Summary on Spherical Weathering Body Processing Method of Shield Tunnel[J];公路工程;2014-02
5 YANG Jun-sheng;ZOU Zhi-lin;LIANG Kui-sheng;YOU Yong-feng;ZHANG Xue-min;XIAO Chao;School of Civil Engineering, Central South University;Beijing Urban Construction Design &Development Group Co.,Limited;China Railway Tunnel Stock Co., Ltd.;;Tunneling characteristics of high-strength bedrock stratum pretreated by blasting[J];岩土工程学报;2014-06
6 DING Rui1,LU Yaobang2,DANG Rujiao2,LI Yang2(1.China Railway Tunnel Group Co.,Ltd.,Luoyang 471009,Henan,China; 2.Technology Center of China Railway Tunnel Group Co.,Ltd.,Luoyang 471009,Henan,China);Pretreatment of Bedrock Intruding into Shield Tunneling Scope by means of Blasting Hole Drilling from Ground Surface and Blasting Underground[J];隧道建设;2013-03
7 WANG Yang,WU Xin-xia,YIN Jian-min,WU Cong-qing,ZHOU Li-ming,AI Kai(Key Laboratory of Geotechnical Mechanics and Engineering of the Ministry of Water Resources, Yangtze River Scientific Research Institute,Wuhan 430010,China);Slope Stability of Earth-Rock Cofferdam During Phased Demolition[J];长江科学院院报;2012-08
8 LI Quan(Guangzhou Blasting Engineering Co Ltd,Guangzhou 510000,China);Analysis and Comparison of Several Calculation Formulas of Specific Charge Underwater Drilling Blasting[J];爆破;2012-01
9 ZHANG Zhong-wei1,REN Ge2,LI Hong-tao2(1.Ertan Hydropower Development Company Ltd,Chengdu 610051,China;2.College of Hydraulic and Hydroelectric Engineering,Sichuan University,Chengdu 610065,China);Explosive Demolition of Intake Cofferdam of Diversion Tunnel on Jingping Ⅱ Hydropower Station[J];爆破;2011-04
Similar Journals
©2006 Tsinghua Tongfang Knowledge Network Technology Co., Ltd.(Beijing)(TTKN) All rights reserved