Case Analysis on Decreasing Temperature of Exhaust Gasfrom Goal-Fired Boiler

SUN Bing,XIE Dong-mei,HU Yue-hong,HUANG Jing(Department of Thermal Engineering,Chengde Petroleum College,Chengde,Hebei 067000,China)  
It is one of the QC subjects of The First Thermal Power Co.Ltd in Changchun in order to decrease the temperature of exhaust gas from 4# coal-fired boiler.This paper discusses some corresponding measures based on field investigation and following reason analysis including persons(operating workers),machines(facilities and instruments)and rules(operation regulations and manage rules)according to its own practical conditions,with the purpose of energy conservation and consumption reduction from itself.
【CateGory Index】: TK229.6
Download(CAJ format) Download(PDF format)
CAJViewer7.0 supports all the CNKI file formats; AdobeReader only supports the PDF format.
【Co-citations】
Chinese Journal Full-text Database 10 Hits
1 LIU Zhan-bin(Shanxi Hepo Power CO.Ltd,Yangquan 045000,China);The Causal Analysis on Coking of Boiler and Measures[J];Journal of Electric Power;2005-03
2 Hou Xiangyang(Zhengzhou Xinli Power Ltd.Co.,Zhengzhou City,450007);Study on Regulation and Test of Combustion Optimization for Coal-fired Boilers[J];Electric Power Construction;2006-06
3 YANG Zhou,YAO Wen(Central Southern China Electric Power Design Institute,Wuhan 430071,China);Discussion on 1 000 MW Unit HV Startup/Backup Power Supply Connection Schemes[J];Electric Power Construction;2008-11
4 GAO Wei,YE Yong-jian(East China Electric Power Design Institute,Shanghai 200063,China);A Reasonable Approach to Determine Indeses of Design Coal[J];Electric Power Construction;2009-02
5 YU Xing-chao(Waigaoqiao No.3 Electric Power Generation Co.,Ltd.,Shanghai 200137,China);Configuration of 1000 MW USC Unit Feed Water Pump for Waigaoqiao No.3 Power Plant[J];Electric Power Construction;2009-02
6 HU Wei-feng, XIE Jing-mei (Zhejiang Beilun Power Plant, Ningbo 315800, China);Feasibility Study on 600 MW Boiler Low-NO_x Combustor Retrofitting[J];Electric Power Construction;2009-03
7 WANG Da-jun1,TAO Yong2(1.Sichuan Electric Power Calibration Testing Institute,Chengdu 610072,China;2.Sichuan College of Architectural Technology,Deyang 618000,China);Experimental Study of Burner Calibration with Laser Technology[J];Electric Power Construction;2009-05
8 ZHANG Xiao-yang,GUO Yang-fu,LIU Zhi,LIU Wen-ping,LI Li-min (ZhangShan Power Plant Co., Ltd. Changye 046021,China);Economics Analysis of On-line Automatic Ball Screening Equipment of Mill in Zhangshan Power Plant[J];Electrical Equipment;2008-04
9 JIANG Hong-xing(Huaneng Ruijin Power Plant,Jiangxi Ganzhou 341108,China);Analysis on Frequency-transducer of Axial-flow Forced Fan[J];Journal of Jiangxi Vocational and Technical College of Electricity;2008-04
10 MA Jun - hua 1 ,LIU Xiao 2 ,WEN Ya 3 ( 1.Jiangsu Electric Power Research Institute Co.,Ltd.,Nanjing210036 ,China ;2.Siemens Power Plant Automation Limited ,Nanjing210003 ,China ;3.Beijing Bootes Electric Power Science&Technology Co.,Ltd.,Beijing100031 ,China );Optimized design of 330MW unit combustion control system[J];Electric Power Automation Equipment;2004-06
China Proceedings of conference Full-text Database 1 Hits
1 ZHU Feng (Anhui Maanshan Wannengda Power Plant Co.,Ltd.,Maanshan 243051,China);Analysis and comparison of tripping turbine after boiler MFT and not tripping turbine after boiler MFT[A];[C];2008
©2006 Tsinghua Tongfang Knowledge Network Technology Co., Ltd.(Beijing)(TTKN) All rights reserved