《Power System Technology》 2005-20
Add to Favorite Get Latest Update

Research on Typical Design for 500kV/330kV Substations and Its Application

GUO Ri-cai1,LI Bao-jin2,LI Ming1 (1.Department of Construction,State Grid Corporation of China,Xicheng District,Beijing 100031,China; 2.China Power Engineering Consulting Group Corporation,Xicheng District,Beijing 100011,China)  
The aim, input conditions and main technical and economical indices of Typical Design for 500kV/330kV substations are presented, according to the main equipments in substation the Typical Design are divided into four basic schemes for GIS. HGIS, porcelain knob circuit breaker and dead tank circuit breaker. The main technical schemes of Typical Designs for 500kV and 330kV substations are emphatically analyzed, the main wiring forms for various voltage grades, short circuit current level and so on are illustrated in detail. The cost estimate and practical application show that Typical Design possesses such features as saving investment, reducing the land occupation, improving power supply reliability and enhancing the flexibility of planning. Finally, a brief introduction to the outlines of Typical Designs being conducted for transmission line, 220kV substation and 110kV substation are given.
【CateGory Index】: TM63
Download(CAJ format) Download(PDF format)
CAJViewer7.0 supports all the CNKI file formats; AdobeReader only supports the PDF format.
【References】
Chinese Journal Full-text Database 4 Hits
1 LI Ming1, XU Xinqian2(1. School of Electrical Engineering, Beijing Jiaotong University, Beijing 10044, China; 2. Jiangsu Electric Power Design Institute, Nanjing 210024, China);Research on Influence of Typical Design on Equipment Manufacturing and Material Processing in Power Grid Engineering[J];Electrical Equipment;2006-05
2 GUO Ri-cai1,YUAN Zhao-xiang2,LI Bao-jin 3 (1.State Grid Corporation of China,Xicheng District,Beijing 100031,China; 2.Jiangsu Electric Power Design Institute,Nanjing 210024,Jiangsu Province,China; 3.China Power Engineering Consultation Group Corporation,Xicheng District , Beijing 100011,China);A Survey on Typical Design of Substations in France and Korea and Relevant Suggestion to Power Network Engineering in China[J];Power System Technology;2006-06
3 GUO Ri-cai~1 XU Zi-zhi~1 LI Xi-lai~2 XU Xiao-dong~3 WANG Jin~2 ZHANG Qiang~1 WU Qi-wei~4 1.Department of Construction,State Grid Corporation of China, Xicheng District, Beijing 100031, China; 2. China Electric Power Consulting Group Corporation, Xicheng District, Beijing 100011, China; 3. Central Southern China Electric Power Design Institute, Wuhan 430071, Hubei Province, China; 4. North ChinaPowerEngineering (Beijing)Co. Ltd., XichengDistrict, Beijing 100011, China;Typical Design of Transmission Lines within Voltage Grades from 110 kV to 500 kV and Its Application[J];Power System Technology;2007-01
4 HOU Jian-she,WU Hui(Henan No.1 Thermal Power Construction Company,Zhengzhou 450012,China);Construction Quality Management of Nanyangxi 500 kV Substation[J];Electric Power Construction;2009-09
【Co-citations】
Chinese Journal Full-text Database 10 Hits
1 WANG Chuan, LI Yan jun (Anhui Kaili Science Technology Co.,LTD., Hefei 230099, China);Switching overvoltage analysis and its restricted measures of vacuum circuit breaker[J];Journal of Anhui Technical College of Water Resources and Hydroelectric Power;2002-02
2 PENG Xiang yun, MAO Qi wu, ZENG Qing gan (Shunde Special Transformer Works, Shunde 528300, China);Calculation and Analysis of Aseismic Performances of Supporting Insulators in Large Shunt Air-Core Reactor[J];Transformer;2001-07
3 RONG Li (Heilongjiang Research Institute of Electric Power Exploration and Design,Harbin 150001,China);Application of GPS Time Synchronism System in Electric Power System[J];Geomatics & Spatial Information Technology;2007-05
4 XIAO Guo-bin(Guangzhou Huasheng Surge Arrester Enterprise Co.,Ltd.,Guangzhou 510288,China);Elbow Arrester with Disconnector for 10kV AC Power System[J];Insulators and Surge Arresters;2005-01
5 WANG Yun-mao1,YAO Hui2,XIAO Xin-hua2(1.Fujian Electric Power Test & Research Institute,Fuzhou 350007,China;2.Fujian Yirong Information Technology Co.,Ltd,Fuzhou 350003,China);Research and development of test equipment typed PST for substation integrative automation system[J];Electrical Measurement & Instrumentation;2007-11
6 WENG Da-gen, XU Zhi-xin (Research Institute of Structural Engineering and Disaster Reduction, Tongji University, Shanghai 200092, China);Understanding of seismic design spectrum for Shanghai[J];Earthquake Engineering and Engineering Vibration;2001-01
7 Yue Maoguang~(1),Wang Dongsheng~(2),Li Hongnan~(1,)Zhai Tong~(3)(1. State Key Laboratory of Costal and Offshore Engineering, Dalian University of Technology, Dalian 116023,China; 2. Institute of Road and Bridge Engineering, Dalian Maritime University, Dalian 116026, China; 3. Institute of Engineering Mechanics, China Earthquake Administration, Harbin 150080, China);Response of power transmission tower-cable system subjected to near-fault ground motions[J];Earthquake Engineering and Engineering Vibration;2005-04
8 LU Hai-quan(Zhejiang Dongyang Power Supply Bureau,Dongyang Zhejiang 322100,China);Application and Improvement Measures of Voltage Quality Control Installation[J];Power Capacitor;2006-04
9 ;Primary study of electric locomotive used in high altitude[J];Electric Power Environmental Protection;2006-02
10 Cao Meigen~1,Xu Zhonggen~1,Liu Zhiyong~2(1.Guangzhou University,Guangzhou City,510405;2.Guangzhou Power Supply Branch Company,Guangzhou City,510620);Dynamic Characteristics Analysis of Combo Steel Tube Tower for Large Crossing Transmission Lines[J];Electric Power Construction;2005-12
【Co-references】
Chinese Journal Full-text Database 10 Hits
1 TANG Yong, XU Bin, XU He-ming (Xuancheng power supply bureau);The exploring and practice of multi-program design and development in 35KV rural substation[J];Journal of Anhui Electric Power College for Staff;2002-03
2 Zhao Shuhua (Guangzhou South Electric Power Constriction Group Ltd.Com.,Guangzhou City,510600);Outline of Executing"Process Management"in Electric Power Engineering Construction[J];Electric Power Construction;2005-02
3 LIU Jun1,MA Zhi-wei2,YANG Xiao-sen1,ZHANG Jun1(1.Beijing Transmission and Distribution Company,Beijing City,102401;2.North China Power Grid Ltd.Co.,Beijing City,100053);Analysis on Project Management of North Beijing 500 kV Substation Construction[J];Electric Power Construction;2006-11
4 ZHANG Yu-fang (National Grid Construction Co.,Ltd,Dongcheng District,Beijing 100005,China);Research on Gap Width of Outdoor Distribution Equipment in 500kV Substations[J];Power System Technology;2005-20
5 GUO Ri-cai1,LI Ming1,XU Xiao-dong2,LAN Hai3 (1.State Grid Corporation of China,Xicheng District,Beijing 100031,China; 2.China Power Engineering Consulting Group Corporation,Xicheng District,Beijing 100011,China; 3.Sichuan Electric Power Corporation,Chengdu 610041,Sichuan Province,China);Research and Suggestions on Speeding up Dissemination and Application of New Technologies for Power Grid Construction[J];Power System Technology;2006-02
6 GUO Ri-cai1,YUAN Zhao-xiang2,LI Bao-jin 3 (1.State Grid Corporation of China,Xicheng District,Beijing 100031,China; 2.Jiangsu Electric Power Design Institute,Nanjing 210024,Jiangsu Province,China; 3.China Power Engineering Consultation Group Corporation,Xicheng District , Beijing 100011,China);A Survey on Typical Design of Substations in France and Korea and Relevant Suggestion to Power Network Engineering in China[J];Power System Technology;2006-06
7 HUANG Hao(Guangdong Power Grid Foshan Gaoming Branch,Foshan 528500,Guangdong Province,China);Feasibility Study and The Functions in Construction Projects of Electric Power System[J];Power System Technology;2007-S1
8 WANG Guang hua,TIAN Yi (Taiyuan Electric Power supply Bureau,Taiyuan,shanxi 030012,China);Several Paints Regarding GIS Equipment Selection for 110 kV city Power Network[J];Shanxi Electric Power;2000-06
9 GUO Xue ying (Taiyuan Power Supply Corporation,Taiyuan,Shanxi 030012,China);Study on the Mode of Development for 110 kV Substation of the City Net[J];Shanxi Electric Power;2002-04
10 HAO Zhi-fang(Yangquan Power Supply Company,Yangquan,Shanxi045000,China);Probe into Matters Concerning the Design of 110 kV Indoor Transformer Station[J];Shanxi Electric Power;2003-S2
【Secondary References】
Chinese Journal Full-text Database 10 Hits
1 WANG Ying-jun Xingtai Electric Power Corporation,Xingtai 054001,China; WU Zheng-rong Hebei Electric Power Corporation,Shijiazhuang 050021,China;Suggestions and the Thought of Counter Icing Snow Calamity Ability for China's Power Grid[J];Electrical Equipment;2008-07
2 YANG Meng,ZHANG Lizi,SHU Juan(North China Electric Power University,Beijing 102206,China);Path Decision-making Considering Environmental Factors in Transmission Planning[J];Automation of Electric Power Systems;2008-15
3 GUO Ri-cai1,XU Zi-zhi1 ,QI Li-zhong2 ,LI Xi-lai3,LI Jin4, ZHANG Lian-ying1,HE Chang-hua5,GUAN Shun-qing6 (1.State Grid Corporation of China,Xicheng District,Beijing 100031,China;2.Hebei Electric Power Investigation Design & Research Institute,Shijiazhuang 050031,Hebei Province,China;3.China Power Engineering Consulting(Group) Corporation,Xicheng District,Beijing 100011,China;4.North China Power Engineering(Beijing) Co., Ltd,Haidian District, Beijing 100761,China;5.Beijing Electric Power Construction Research Institute of SGCC,Xuanwu District,Beijing 100055, China;6.Northwest Electric Power Design Institute,Xi’an 710032,Shaanxi Province,China);General Situation of Typical Transmission Line Design in USA and Its Enlightenment to Design and Construction of Power Grids in China[J];Power System Technology;2007-12
4 ZHANG Yu-fang,SONG Ji-ming (State Grid AC Project Construction Co., Ltd,Dongcheng District,Beijing 100005,China);Discussion on Opening-Closing-Opening Test of Circuit Breaker in Start-up and Commissioning of 500 kV AC Transmission System[J];Power System Technology;2007-17
5 WANG Sheng-xue1,WU Guang-ning1,FAN Jian-bin2,ZHOU Jun2,JIANG Wei1(1.School of Electrical Engineering,Southwest Jiaotong University,Chengdu 610031,Sichuan Province,China;2.China Electric Power Research Institute,Haidian District,Beijing 100192,China);Study on Flashover of Suspension Insulator String Caused by Windage Yaw in 500kV Transmission Lines[J];Power System Technology;2008-09
6 LU Zhi-gang,CHEN Jin-yang(Key Lab of Power Electronics for Energy Conservation and Motor Drive of Hebei Province(Yanshan University),Qinhuangdao 066004,Hebei Province,China);Planning of Substation and Switching Station for Distribution Network Based on Load Rate[J];Power System Technology;2009-06
7 HAN Feng,LI Hui,WANG Zhi-dong,LIU Jian-qin,WANG Le (State Power Economic Research Institute,Xuanwu District,Beijing 100761,China);Development Course and Planning Method of French Power Grid and Its Enlightenment for Us[J];Power System Technology;2009-08
8 DAI Gang-ping (Zhejiang Shenda Tower Limited Company,Hangzhou 311232,China);Study on Welding Quality Control of Ball Nodes of Transmission Line Steel-tube Tower[J];Electric Power Construction;2009-08
9 XIAO Dong-ping,HE Wei,YANG Fan,ZHANG Zhan-long,TANG Ju(State Key Laboratory of Power Transmission Equipment & System Security and New Technology,Chongqing University,Chongqing 400044,China);Power Frequency Electric Field Calculation and Span Selection for UHV Transmission Lines with Different Meteorological Conditions[J];High Voltage Engineering;2009-09
10 WU Kun;Research on the Control of the Cost, Schedule and Quality in the Construction of the Power Grids[J];Sci-Tech Information Development & Economy;2007-33