Method for Scheduling Forecasting with Time-based Earned Value Technology

GAO Peng1,FENG Jun-wen1,WANG Hua-ting2(1.School of Economics and Management,Nanjing University of Science & Technology,Nanjing 210094,China;2.The State Key Laboratory of Intelligent Technology and System,Tsinghua University,Beijing 100084,China)  
With the limitation of cost-based EVT for scheduling forecasting,this paper develops a new method called EVT based on time.Furthermore,each forecasting formula is proposed according to different project status.Finally,a given example demonstrates that compared with planned value and earned project time methods,the proposed method can more accurately reflect scheduling performance near the termination phase(the latter one third phase),even in the whole project life cycle of the project.