Risk Assessment and Management Measures for Shanghai Rail Transit Construction

Zhang Hui,Li Wenyong,Ni Zhifang Shanghai Jianke Project Management Co.,Ltd.,200032,Shanghai,China  
By using a fuzzy comprehensive evaluation method based on Analytic Hierarchy Process,risk assessment of Shanghai Rail Transit Line 12 Project is carried out.Then the risk ratings are obtained,including total risk of the whole project,construction risk of the civil engineering structures,track engineering and electromechanical installations,risk of safety and health,as well as risk of environmental influence.Moreover,risks of key construction joints,such as the transfer stations in complicated environment,the river-crossing shield tunnel and closely-spaced overlap shield tunnel are analyzed and assessed.Furthermore,some risk management measures are proposed according to the risk assessment results,which can be used as the guide of risk tracking and risk controlling,also be used as the basis of the project insurance.
【Fund】: 国家“十一五”科技支撑计划项目(2006BAJ01B04-02);; 上海市科学技术委员会科研计划项目(07QB14030)
【CateGory Index】: U239.5
Download(CAJ format) Download(PDF format)
CAJViewer7.0 supports all the CNKI file formats; AdobeReader only supports the PDF format.
【Citations】
Chinese Journal Full-text Database 4 Hits
1 ZHOU Hong-bo1,2,NI Zhi-fang3,GAO Wen-jie1(1.Shanghai Jianke Project Management Co.Ltd.Shanghai.200032.China;2.Tongji University.Shanghai.200092.China.3.Shanghai Yangpu Metro Line Development Co.Ltd Shanghai 200010,China);Study on Risk Assessment and Control Measures for the Construction Safety of Metro Line Project[J];Chinese Journal of Underground Space and Engineering;2008-05
2 Zhang Xiaoli Shenzhen Metro Group Co.,Ltd.,518026,Shenzhen,China;Research on the Overall Risk Assessment of Urban Rail Transit Enterpreses[J];Urban Mass Transit;2009-10
3 ZHOU Hong-bo~(1,2)(1.Shanghai Research Institute of Building Sciences,Shanghai 200032,China;2.Shanghai Jianke Project Management Co.,Ltd.,Shanghai 200032,China);Risk Assessment of Deep Foundation Pit by Using Fuzzy Comprehensive Evaluation Method Based on Bayesian Networks[J];Journal of Shanghai Jiaotong University;2009-09
4 HE Xi-xing,ZHOU Hong-bo,YAO Hao(Shanghai Jianke Project Management Co.,Ltd.,Shanghai 200032,China);Construction risk identification and assessment of a deep foundation pit in Shanghai[J];Chinese Journal of Geotechnical Engineering;2006-S1
【Co-citations】
Chinese Journal Full-text Database 10 Hits
1 ZHOU Hong-bo1,2,NI Zhi-fang3,GAO Wen-jie1(1.Shanghai Jianke Project Management Co.Ltd.Shanghai.200032.China;2.Tongji University.Shanghai.200092.China.3.Shanghai Yangpu Metro Line Development Co.Ltd Shanghai 200010,China);Study on Risk Assessment and Control Measures for the Construction Safety of Metro Line Project[J];Chinese Journal of Underground Space and Engineering;2008-05
2 CHEN Xiao-yong1,GAO Guang-yun1,LI Wei2(1.Key Laboratory of Geotechnical and Underground Engineering of Ministry of Education,Tongji University,Shanghai 200092,China;2.Shanghai Shenyuan Geotechnical Engineering Co.,Ltd.,Shanghai 200011,China);The Risk Analysis of Retaining Structures in Deep Excavation[J];Chinese Journal of Underground Space and Engineering;2009-S2
3 Hao Fengtian1,Zhao Ping2(College of Civil Engineering,Xi′an University of Architecture and Technology,Xi′an,710055,China);Risk Study on Subway Construction Based on Reliability Theory[J];Chinese Journal of Underground Space and Engineering;2011-02
4 Li Jiu;Fuzzy Synthetic Judging Optimization in Deep Foundation Pit Supporting Scheme[J];Urban Roads Bridges & Flood Control;2007-09
5 TANG Wen-bin1,2,ZHANG Fei-lian1 (1.School of Civil Engineering and Architecture,Central South University,Changsha 410075;2.School of Economy and Management,Changsha University of Science and Technology,Changsha 410114,China);The Risk of Evaluation Methodology of Urban Rail Transit Investment and Financing[J];Systems Engineering;2011-01
6 Wu Nan(Kunshan Rail Transit Investment and Development Co.Ltd.,Kunshan,Jiangsu 215332,China);Study of Safety Index System Based on Risk Assessment in the Construction of Deep Excavation Project[J];Chinese Journal of Underground Space and Engineering;2011-03
7 Li Luning Shenzhen Metro Group Co.,Ltd., 518026,Shenzhen,China;On Group Control Mode of Urban Mass Transit Enterprises[J];Urban Mass Transit;2011-07
8 SHE Dunxian~(1,2,3*),YANG Xiaohua~1 and XIA Jun~2 1 School of Environment,Beijing Normal University,Beijing 100875,China; 2 Key Laboratory of Water Cycle & Related Land Surface Processes,Institute of Geographic Sciences and Natural Resources Research,CAS,Beijing 100101,China; 3 Graduate University of Chinese Academy of Sciences,Beijing 100049,China;The Evaluation of the Integrated Risk for the South-to-North Water Transfer Project Using the Bayesian Network Theory[J];资源与生态学报(英文版);2010-03
9 DAI Jia-li1,ZHANG Jian-xin1,DU Wen-qi2,LIU Nai-di2(1.Tianjin Institute of Urban Construction,Tianjin Key Laboratory of Soft Soil Characteristics and Engineering Environment,Tianjin 300384,China;2.Tianjin Anju Building and Development General Co.,Tianjin 300050,China);Safety assessment method for the influence of deep foundation pit on surrounding environment[J];Journal of Hebei University of Engineering(Natural Science Edition);2011-03
10 Gao Wenjie~1,Zhou Hongbo~1,Huang Yu~2,Sun Qingyang~1(1.Shanghai Jianke Project Management Co.,Ltd.,Shanghai 200032,China;2.Tongji University,Shanghai 200092,China);Construction Risk Analysis and Assessment on Zifeng Building in Nanjing[J];Construction Technology;2008-S1
【Co-references】
Chinese Journal Full-text Database 10 Hits
1 HUANG Hong-wei , BIAN Yi-hai (Department of Geotechnical Engineering, Tongji University, Shanghai 200092);Risk Management in the Construction of Deep Excavation Engineering[J];;2005-04
2 CHEN Xiao-yong1,GAO Guang-yun1,LI Wei2(1.Key Laboratory of Geotechnical and Underground Engineering of Ministry of Education,Tongji University,Shanghai 200092,China;2.Shanghai Shenyuan Geotechnical Engineering Co.,Ltd.,Shanghai 200011,China);The Risk Analysis of Retaining Structures in Deep Excavation[J];Chinese Journal of Underground Space and Engineering;2009-S2
3 LIU Hui~1,QU Wei-lian~1,YUAN Run-zhang~2 (1.Institute of Civil Engineering and Architecture, Wuhan University of Technology, Wuhan 430070,China;essing, Wuhan University of Technology, Wuhan 430070,China);Optimum sensor placement for structural damage detection based on sensitivity study[J];Earthquake Engineering and Engineering Vibration;2003-06
4 CAI Jing1,2 , WU Zhi-shen3 , LI Zhao-xia2 (1. College of Civil Engineering, Nanjing University of Technology, Nanjing 210009, China; 2. College of Civil Engineering, Southeast University, Nanjing 210096, China; 3. Dept. of Urban & Civil Eng., Ibaraki Univ., Hitachi , 316-8511, Japan);STATISTICAL APPROACH TO EVALUATING THE STATUS OF AN EXISTING STRUCTURE USING STATIC TEST DATA[J];Engineering Mechanics;2004-06
5 ZHANG Zheng-hua,BI Dan,LI Zhao-xia(Department of Engineering Mechanics,Southeast University,Nanjing 210096,China);RESEARCH ON OPTIMAL PLACEMENT OF STRAIN SENSORS IN DECK OF CABLE-STAYED BRIDGES BASED ON MULTI-SCALE MODELING AND ANALYSIS[J];Engineering Mechanics;2009-01
6 LI Zheng-nong,HU Shang-yu,LI Qiu-sheng(Ministry of Education Key Laboratory of Building Safety and Energy Efficiency,Hunan University,Changsha,Hunan 410082,China);OPTIMAL TWO-DIMENSIONAL LAYOUT OF MEASURING POINTS FOR STRUCTURAL EXPERIMENTS[J];Engineering Mechanics;2009-05
7 WU Zi-yan,HE Yin,JIAN Xiao-hong(School of Mechanics,Civil Engineering and Architecture,Northwestern Polytechnic University,Xi'an,Shaanxi 710072,China);OPTIMAL SENSOR PLACEMENT BASED ON SENSITIVITY ANALYSIS OF STRUCTURAL DAMAGE[J];Engineering Mechanics;2009-05
8 JIANG Shao-fei1,YANG Bo2,WU Zhao-qi1(1.College of Civil Engineering,Fuzhou University,Fuzhou,Fujian 350108,China; 2.School of Civil Engineering,Shenyang Jianzhu University,Shenyang,Liaoning 110168,China);SENSOR ARRANGEMENT METHOD BASED ON VULNERABILITY ANALYSIS FOR A TRUSS BRIDGE[J];Engineering Mechanics;2010-S2
9 TAN Dong-lian~1,XIAO Ru-cheng~2 (1.Highway College,Chang'an University,XI'an 710064,China;2.Bridge Engineering College,Tongji University,Shanghai 200092,China);Optimal Placement of Static Strain Sensors of Complicated Bridge Structure in Bridge Monitoring System[J];Highway;2006-06
10 Ma Jiyong Yang Binmei;On the Theory of Optimizing Layout of Test Date[J];;1992-04
China Proceedings of conference Full-text Database 1 Hits
1 Bian Yihai,Huang Hongwei (The Department of Geotechnical Engineering of Tongji University, Shanghai,200092, P.R.China);RISK ANALYSIS IN THE CONSTRUCTION OF DEEP EXCAVATION ENGINEERING BASED ON DEPENDABILITY METHOD[A];[C];2005
【Secondary Citations】
Chinese Journal Full-text Database 10 Hits
1 ZHOU Hong-bo~1,HE Xi-xing~1,JIANG Jian-jun~2,CAI Lai-bing~1 (1.Shanghai Jianke Project Management Co.Ltd.,Shanghai 200032,China;2.Sichuan Province C.D.Highway Planning,Survey,Design and Research Institute,Chengdu 610041,China);Risk Identification and Handling in Construction of Metro Shield Tunnel Project[J];Chinese Journal of Underground Space and Engineering;2006-03
2 ZHOU Hong-bo1,2,NI Zhi-fang3,GAO Wen-jie1(1.Shanghai Jianke Project Management Co.Ltd.Shanghai.200032.China;2.Tongji University.Shanghai.200092.China.3.Shanghai Yangpu Metro Line Development Co.Ltd Shanghai 200010,China);Study on Risk Assessment and Control Measures for the Construction Safety of Metro Line Project[J];Chinese Journal of Underground Space and Engineering;2008-05
3 Gu Sufei(Operation Branch of Shenzhen Metro Co., Ltd., Shenzhen 518040);Layout and Application of Operation and Safety Management System in Shenzhen Metro[J];Urban Rapid Rail Transit;2006-01
4 Zhu Shengli1 Wang Wenbin1 Liu Weining2 Lu Meili2(1. Beijing MTR Construction Administration Corporation, Beijing 100037;2. Beijing Jiaotong University, Beijing 100044);Discussion on Risk Management of Subway Projects[J];Urban Rapid Rail Transit;2008-01
5 YANG Qing ① JIAO Jian kui ① LUAN Mao tian ① SHI Da zhai ②(①Dalian University of Technology, Dalian 116024) (②Baotou University of Iron and Steel Technology, Baotou 014010);RELIABILITY ANALYSIS AND RISK EVALUATION OF THE SLOPE ENGINEERING[J];JOURNAL OF ENGINEERING GEOLOGY;2000-01
6 Zhang Hong,Liu Yong,Dong Sanxi Shenzhen Metro Co.,Ltd.,518026,Shenzhem,China;Experiences of Investment/Financing on Metro in Seven World Cities[J];Urban Mass Transit;2007-10
7 PAN Mao qing, HUI Ke xiang, ZHANG You_lai, WANG Qi (The First Aeronautical Institute of Air Force,Xinyang 464000,China);The application of Bayesian to evaluate relay reliability[J];Relay;2003-05
8 LI Minghui(Department of Accounting,Nanjing University,Nanjing 210093,China);Organizational Structure of Risk Management[J];Science of Science and Management of S.& T.;2008-01
9 ZHAO Honga,LI Ya-jub,SONG Taoa(a.School of Management,b.Department of Accounting,Shenyang University of Technology,Shenyang 110178,China);Study on engineering project risk management based on Bayesian network[J];Journal of Shenyang University of Technology(Social Science Edition);2008-03
10 Qin Binjun Shanghai Edward Shipbuilding Co.Ltd, Shanghai, China Zhang Shengkun School of Naval Architecture & Ocean Engineering, Shanghai Jiaotong University;Risk Assessment of Dynamic Process[J];JOURNAL OF SHANGHAI JIAOTONG UNIVERSITY;1998-11
China Proceedings of conference Full-text Database 1 Hits
1 ZHAO Lin, ZHOU Hongbo, DengShaolun ( Building Engineering Department, Tongji University, Shanghai 200092 P.R.China) ( Build and Manage Consulting Limited Company Of Shanghai Research Institute of Building Science, Shanghai 200032 P.R.China);RESEARCH on AHP METHOD APPLffiD in THE FIELD of ENGINEERING PROJECT RISK ASSESSMENT[A];[C];2005
©2006 Tsinghua Tongfang Knowledge Network Technology Co., Ltd.(Beijing)(TTKN) All rights reserved