Contractor-Oriented Risk Analysis of EPC Hydropower Project Cost

LIU Dong-hai1,2,SONG Hong-lan1(1.School of Civil Engineering,Tianjin University,Tianjin 300072,China; 2.State Key Laboratory of Hydraulic Engineering Simulation and Safety,Tianjin University,Tianjin 300072,China)  
Fixed price contract is usually employed in the engineering-procurement-construction(EPC) hydropower project.However,project cost is difficult to manage because many uncertainty factors exist.There is a risk for the general contractor to accomplish an EPC project with a fixed price contract.Therefore,it is important for a general contractor to make quantitative analysis of uncertainty factors related to project cost in order to give a competitive bidding with reasonable contract price and then implement effective cost control during the whole construction period. First,this paper identifies main cost risks of an EPC hydropower project and proposes a contractor's cost model by considering price uncertainty,interest rate,natural condition,engineering technology and owner's credit.The cost contains not only the budgetary estimate of design(A),but also the additional expected costs including materials price inflation cost(a),and the interest of contractor's advanced cash because of owner's overdue payment(G),and the increased cost of modification design that are susceptible to natural condition and engineering technology risks(L). Second,we discuss the methods used to calculate materials price inflation cost,the interest of contractor's advanced payment and the increased cost.We estimate the price inflation cost a and predict the price fluctuation by using the average growth of main materials price index of hydropower project.Considering unfavorable natural conditions of engineering geology,hydrology and climate,and project technique risks,PERT(Program Evaluation and Review Technique) and Three Point Evaluation methods are employed to measure the increased cost of modification design L.Additionally,the maximum delayed months and monthly repayment probability are determined by experts according to owner's credit and financial capability.The interest of contractor's advanced payment during the whole construction period G can be calculated to estimate the monthly budgetary of design and the repayment probability. Finally,the complex contractor's cost model with some random variables is solved by the Monte-Carlo method.The cost distribution and monthly expected cost cash-flow,as well as the cost control risk of general contractor can be simulated quantitatively.Furthermore,the general contractor cost of an EPC hydropower project in Yunnan province China is analyzed using the proposed methods.The finding provides strong support for the general contractor to make reasonably decision on bidding price,risk compensation,and cost control in the construction process.
【Fund】: 国家自然科学基金资助项目(51079096);国家自然科学基金创新研究群体科学基金资助项目(51021004);; 教育部新世纪优秀人才计划资助项目(NCET-08-0391)
【CateGory Index】: F285;TV512
Download(CAJ format) Download(PDF format)
CAJViewer7.0 supports all the CNKI file formats; AdobeReader only supports the PDF format.
【References】
Chinese Journal Full-text Database 1 Hits
1 GAO Qiang;Northwest Electric Power Construction Corporation;;Analysis on Legal Risk of EPC Project Contract[J];Value Engineering;2013-29
【Citations】
Chinese Journal Full-text Database 5 Hits
1 LIU Dong-hai,SONG Hong-lan(School of Civil Engineering,Tianjin University,Tianjin 300072,China);Risk analysis and comprehensive evaluation of risks in EPC hydropower engineering[J];Water Sciences and Engineering Technology;2010-01
2 WANG Zhenqiang~(1,2), ZHONG Denghua~2(1. School of Economics and management, Tianjin University of Technology, Tianjin\ 300191;2.School of Civil Engineering, Tianjin University, Tianjin\ 300072);Application study of project financial risk analysis of giant hydropower project[J];Journal of Hydroelectric Engineering;2004-05
3 QIANG Maoshan1,CAI Hangqing1, LI Guohua2(1Tsinghua University; 2China Hydropower Project Consultant Group Corporation);Research on the approach of estimating contingency reserve for the Investments of Hydraulic Engineering Project[J];Water Power;2003-03
4 Li Jige, Guo Jianxin, Chen Hao (Hydropower and Water Resources Planning and Design General Institute, Beijing 100120);Review and Prospect of the Issuance of Price Indexes of Hydropower Project[J];Water Power;2009-06
5 Cai HangQing1,2 Qiang Maoshan2(1.China North Industries Corp.,Beijing 100053,China;2.TsingHua University,Beijing 100084,China);A study on the mathematical estimation model of contingency reserve for investments in hydro-electric engineering project[J];China Civil Engineering Journal;2006-07
【Co-citations】
Chinese Journal Full-text Database 10 Hits
1 Li Weifang;Risk Analysis and Countermeasures in Bid Stage of EPC Contract Project[J];Anhui Architecture;2011-03
2 SHAN Xiu-li1,SUN Qiu-bai2 (1.School of Higher Vocational Technology,University of Science and Technology Liaoning,Anshan 114051,China;2.President Office,University of Science and Technology Liaoning,Anshan 114051,China);Risk analysis and evaluation on investment in high-new-tech project[J];Journal of University of Science and Technology Liaoning;2008-05
3 JIN Cheng-xiao,YU Ting-ting (Center for Quantitative Economics Research,Jilin University,Changchun 130012,China);Research on Monitoring and Early Warning of Our Manufacturing Industrial Security Based on BP Neural Network[J];Journal of Beijing University of Technology(Social Sciences Edition);2010-01
4 YANG Hong-tao~1,LI Gui-jun~2 (1.School of Business and Economics,East China University of Science and Technology,Shanghai 200237,China;2.Department of Investment,the Central University of Finance and Economics,Beijing 100081,China);Fuzzy Comprehensive Evaluation on Project Customer Relationship Management[J];Commercial Research;2006-10
5 LI Bing (School of Business Administration, Chongqing University, Chongqing 400044,China);On Fuzzy Comprehensive Assessment of the Effects of Enterprise Technological Innovation[J];Journal of Chongqing Institute of Technology Management;2002-05
6 PENG Yan(School of Economics and Management,North China Electric Power University,Beijing 102206,China);A Gray Relation Analysis of the Risk Evaluation of the Construction Contractors[J];Journal of Hunan Institute of Engineering(Social Science Edition);2011-02
7 ZHANG Chun-li,ZHANG Hong(CCCC First Highway Consultants Co.,Ltd.,Xi'an 710075,China);Research on Project Cost Management of Highway Design-Build Mode[J];Highway;2013-06
8 SHEN Liang-feng (Department of Civil Engineering of Xiangtan Polyechnic University,Xiangtan 411201,China);Analytic hierarchy process applying in construction project preferential evaluation[J];Journal of Heilongjiang Commercial College (Natural Sciences Edition);2002-06
9 LIU Chang-Ping CHANG Qing (Department of Architecture,Gausu Industry Polytechnic College,Tianshui 741025,China);The Model of Multi-factor Fuzzy Comprehensive Evaluation of the Risk in the Development of Real Estate[J];Construction Management Modernization;2007-03
10 CHEN Liwen,WANG Yuanming,LIU Jinxia;Research on Contingency Reserves of Construction Project Cost[J];Construction Economy;2006-11
【Co-references】
Chinese Journal Full-text Database 10 Hits
1 Wang Shu;He Shoukui(School of Management,Chongqing Jiaotong University,Chongqing 400074,China);A Review of PPP/BOT Project Risk Assessment in China[J];Value Engineering;2012-15
2 LI Wen-yi,BAI Qiang,NIE Xiang-tian(North China University Of Water Conservancy And Hydroelectric Power,zhengzhou Henan 450011);Multi-Hierarchical Fuzzy Comprehensive Evaluation of Employer Risk of Hydropower Projects[J];South-to-North Water Transfers and Water Science & Technology;2007-03
3 WANG Hong-wei,SUN Jian-feng,WU Hai-xin,YU Jian-xing(School of Civil Engineering,Tianjin University,Tianjin 300072,China);Research on ERM system for major modern construction project[J];Water Resources and Hydropower Engineering;2006-02
4 Tang Wenzhe1,Qiang Maoshan1,Lu Youmei1,Chen Yunhua2,Peng Qingfeng2(1.School of Civil Engineering,Tsinghua University,Beijing 100084; 2.Ertan Hydropower Development Company Ltd,Chengdu Sichuan 610021);Research on Management of Partnership in Construction[J];Water Power;2008-03
5 ZHANG Jing1,FU Jin-qiang2,ZHANG Fa-yu1,LI Yu-qin1(1.School of Civil Engineering,Tianjin University,Tianjin 300072,China;2.TEDA Chemical Industrial Park Corporation,Tianjin 300480,China);Investment Risk Analysis of Hydropower Project and Its Application[J];Journal of Tianjin University(Social Sciences);2008-03
6 Sun Jide (Research Institute of Project Administration & Management, Tongji University );DESIGN-BUILD CONTRACTING IN CONSTRUCTION PROJECTS[J];China Civil Engineering Journal;2003-09
7 ZHOU Fang-sheng (Research Institute for Fiscal Science,Ministry of Finance,P.R.China,Beijing 100036,China);Explaining on“Comprehensive Risk Management Guidance for Central Enterprise”[J];Shaanxi Electric Power;2007-03
8 LU Shao-kai, QIN Ting-dong(School of Economics and Management, Southwest Jiaotong University, Chengdu, 610031, China);A Research of Supply Chain Management in Engineering Projects[J];Journal of Southwest Jiaotong University(Social Sciences);2005-01
9 GAO Zhi-qiang,ZHANG Meng-lin (Department of Risk Management & Insurance,Nankai University,Tianjin 300071,China);Risk aggregation in ERM system[J];Systems Engineering-Theory & Practice;2009-12
10 ZHANG Wei-gong1,2,HE Jian-min1,DING De-chen1(1.School of Ecnomics and Management,Southeast University,Nanjing 211189; 2.Yangguang Property Insurance Company,Beijing 100020);Overview the Enterprise Risk Management[J];Soft Science;2008-12
【Secondary Citations】
Chinese Journal Full-text Database 8 Hits
1 ZHANG Lian-ying,GOUFO Yemtsa,YANG Xiang(Management School of Tianjin University,Tianjin 300072, China);Contractor's Risk Management under Conditions of Contract for EPC/Turnkey Project[J];China Harbour Engineering;2003-06
2 QIANG Maoshan1,CAI Hangqing1, LI Guohua2(1Tsinghua University; 2China Hydropower Project Consultant Group Corporation);Research on the approach of estimating contingency reserve for the Investments of Hydraulic Engineering Project[J];Water Power;2003-03
3 Liu Zhihua (Beijing);Progress Control for Entire Project Contract[J];PETROLEUM ENGINEERING CONSTRUCTION;1998-03
4 ZHANG Shui-bo, ZHANG Lei, GAO Yuan(School of Management, Tianjin University, Tianjin 300072, China);On the Integration of Indicators of Bid Evaluation Under Design-Build/EPC Project Delivery Approach[J];Journal of Tianjin University (Social Sciences);2005-02
5 Hu Wenxiu;The Micro-Computer Simulation for Project Probability Analysis by Using Monte Carlo Technique[J];JOURNAL OF XI'AN UNIVERSITY OF TECHNOLOGY;1995-01
6 Chen Xuezhong Li Guanghong Department of Business Administration, Shandong Institute of Building Materials, Jinan 250022;An AHP Model Applied to Investment Project Selection[J];Systems Engineering and Electronics;2001-02
7 ZHOU Hui-ren1,ZHENG Pi-e1,QIN Wan-feng2,ZHANG Yang2(1.School of Management,Tianjin University,Tianjin 300072;2.School of Management,Shandong University,Jinan 250100);Multiple Attribute Group Decision-making Approach Based on Entropy and Maximizing Deviations[J];Soft Science;2008-03
8 WANG Zhen -qiang 1 ,LIU Yu -jie 2 ,YU Jiu -ru 3 (1.School of Construction Engineering,Tianjin University,Tianjin 300072,China;2.China Henan International Cooperation limited Corporation,Z hengzhou 450004,China;3.Manageme nt School,Tianj;Applying Research of SCERT on Risk An alysis and Management of Large Project[J];China Soft Science;2002-07
©2006 Tsinghua Tongfang Knowledge Network Technology Co., Ltd.(Beijing)(TTKN) All rights reserved