Design and analysis of joint of slab-column of underground engineering by top-down method

SHEN Kai-peng1,WEI Xi-ling2,JIA Jian-hua2,XIANG Wei-ming1(1.School of Civil Engineering,Guangzhou University,Guangzhou 510006,China; 2.Guangzhou Air Defence Institute of Architectural Design Co.,Ltd.,Guangzhou 510500,China)  
According to the stress problem coming from change in the form of nodes of slab-column structure by Reversed Construction for underground engineering,in this paper,we introduce the construction technology of Reversed and the design approach of slab-column connections of an underground project,studying the stress of the ring beam with using finite element software.The paper verifies the reliability of the use of ring beam in the connections,checks the strength of the outsourcing column,and summarizes the characteristics of the ring beam used in Reversed of underground engineering.
【CateGory Index】: TU93
Download(CAJ format) Download(PDF format)
CAJViewer7.0 supports all the CNKI file formats; AdobeReader only supports the PDF format.
【References】
Chinese Journal Full-text Database 1 Hits
1 PENG Tao;Shanghai Construction No.1(Group) Co.,Ltd.;;Reversed Construction Technology for Beam-Column Joints in Profiled Steel Structure[J];建筑施工;2015-07
【Citations】
Chinese Journal Full-text Database 8 Hits
1 GAO Xi-liang1,LUO Zhi-yong1,LAI Yun-jin2,GAO Yan-bin2 (1.China Railway Eryuan Engineering Group Co.Ltd.,Chengdu,Sichuan 610031,China;2.Tongji University,Shanghai 200092,China);Design and Calculation Analysis of Joint of Beam-column Constructed with Top-down Method[J];铁道工程学报;2011-02
2 JIANG Juan,QI Bin,LIU Guo-bin (1.Department of Geotechnical Engineering,Tongji University,Shanghai 200092,China;2.Key Laboratory of Geotechnical and Underground Engineering of the Ministry of Education,Tongji University,Shanghai 200092,China);Factors and prediction on deformation of soldier piles in deep foundation pits in soft area[J];岩土工程学报;2008-S1
3 WAN Zhi-hui1,LU Zhong-wei1,DAI Bin 2(Shanghai Bao Steel Construction Group,Shanghai 201900,China);Application of reverse construction technology in Shanghai Cao’an Commercial and Trade City[J];岩土工程学报;2006-S1
4 Wang Weidong,Xu Liang,Huang Shaoming(Shanghai Xiandai Architectural Design Group Co.,Ltd.,Shanghai 200041,China);Design and Practice of Large-scale Individual Underground Garage with Top-down Construction Method[J];建筑结构;2006-11
5 ZHAO Qi~1,XIE Jian-bin~1,MAO Zhen-wei~1(1.Shanghai NO.2 Construction Corporation,Shanghai 200080,P.R.China);Design and Construction of the Joint Node Used in the Deep Foundation by Topdown Construction Method[J];地下空间与工程学报;2006-04
6 Xu Sunjie Huang Jinliang Rao Xiejun Fan Caizhong (Fujian Geology Mineral Construction Group Company Fuzhou 350003);Stiffness Coulumnar Pile Construction Tecnology Of the Top - down Construction Method Applied In Soft Soil Foundation and Basement in Shanghai[J];福建建筑;2005-Z1
7 DENG Wen-long (Shanghai NO.2 Construction Co.Ltd, Shanghai 200080, China);The Top-down Construction Technique for Super Foundation of Changfeng Building[J];地下空间与工程学报;2005-04
8 Jiang Shu Jie;Application and Prospective Review on Reserved Construction Method for Urban Underground Space Development[J];建筑施工;2004-04
【Co-citations】
Chinese Journal Full-text Database 10 Hits
1 PENG Tao;Shanghai Construction No.1(Group) Co.,Ltd.;;Reversed Construction Technology for Beam-Column Joints in Profiled Steel Structure[J];建筑施工;2015-07
2 LONG Libo;Shanghai Construction No.2 (Group) Co.,Ltd.;Shanghai Center of Top-Down Method in Construction Engineering;;Experimental Study on Treatment Process of Structural Construction Joint in Later Period of Reversed Construction Method[J];建筑施工;2015-05
3 ZHAO Xiang;WANG Jieguang;College Civil and Architectural Engineering,Guilin University of Technology;;Application of the Reversed Construction Technology in Deep Excavations[J];土工基础;2014-06
4 Sun Suwen;Tan Wen;Que Guang;Zhang Jihong;Zhang Rong;Huang Yingbo;China Construction(Shenzhen) Design International;Wongtee Realestate Group Co.,Ltd. Shenzhen;;Up-Down Construction Design Method of the Gangxia Wongtee Tall Building[J];广东土木与建筑;2014-09
5 Chen Zhengang;Zhang Rongcan;Wang Kanrong;Zhejiang Zhongcheng Construction Group Co., Ltd.;;Construction Technology of Cover Excavation Method Applied to Urban Underground Space Development[J];建筑施工;2014-08
6 Xiang Weiming;Shen Kaipeng;School of Civil Engineering,Guangzhou University;Xiaonan Engineering Quality Supervision and Management Center;;Study on Structural Deformation of Oversize Underground Spacein Coastal Area by the Top-down Method[J];特种结构;2014-01
7 CHEN Ming;LI Jingpei;Department of Geotechnical Engineering,Key Laboratory of Geotechnical and Underground Engineering of Ministry of Education,Tongji University;;INFLUENCE OF EXCAVATION PROCESS IN SAND ON ERECT COLUMN PILES[J];力学与实践;2014-01
8 Huang Zhengrong;Wang Xianyong;Yu Haiyang;Zhou Xuemei;;Construction Technology for Frame Node of Post-pouring Square Ring Beam with Column Hoop[J];重庆建筑;2013-12
9 Jing Shaodong;Shengli Oilfield Shengli Engineering & Consulting Co.Ltd;;Numerical Analysis of Pit Displacement in Strata of “Soil-rock” Dualistic Structure at Top-down Work[J];地下空间与工程学报;2013-06
10 CHEN Ming,LI Jingpei(1.Tongji University,Shanghai 200092,China;2.Key Laboratory of Geotechnical and Underground Engineering of Ministry of Education,Tongji University,Shanghai 200092,China);Analysis on Influence of Excavation Process in Soft Soil Area on Erect Column Piles[J];路基工程;2013-04
【Co-references】
Chinese Journal Full-text Database 6 Hits
1 RAO Chun-wu;ZHU De-kang;ZHAO Yong-hua;LI Huan;CSCEC Strait Construction and Development Co.Ltd.;;Study on the Effective Methods of Connecting Concrete Beamto Steel Column in SRC Structure[J];工程建设与设计;2014-09
2 SHEN Kai-peng1,WEI Xi-ling2,JIA Jian-hua2,XIANG Wei-ming1(1.School of Civil Engineering,Guangzhou University,Guangzhou 510006,China; 2.Guangzhou Air Defence Institute of Architectural Design Co.,Ltd.,Guangzhou 510500,China);Design and analysis of joint of slab-column of underground engineering by top-down method[J];广州大学学报(自然科学版);2012-06
3 ZHU Jin-feng;On selection of beam-column joint of top-down method construction[J];山西建筑;2011-28
4 GAO Xi-liang1,LUO Zhi-yong1,LAI Yun-jin2,GAO Yan-bin2 (1.China Railway Eryuan Engineering Group Co.Ltd.,Chengdu,Sichuan 610031,China;2.Tongji University,Shanghai 200092,China);Design and Calculation Analysis of Joint of Beam-column Constructed with Top-down Method[J];铁道工程学报;2011-02
5 Shi Zhenghua~1,Yao Gang~1,Chen Gelin~2(1.School of Civil Engineering,Chongqing University,Chongqing 400045,China;2.Guangsha Chongqing First Construction(Group) Co.,Ltd.,Chongqing 400053, China);Quality Control of Reverse Construction in Chongqing Huimei Building[J];施工技术;2009-08
6 ;Haunch-Adding Treatment for Slab-Beam and Middle-Supporting-Column Joint in Basement Built with Semi-Reversed Construction Method[J];建筑施工;2006-10
【Secondary Citations】
Chinese Journal Full-text Database 10 Hits
1 JIANG Juan~1,DIAO Peng~2(1.Tongji University,Shanghai 200092,China;2.China Aviation Investigation Design and Research Institute,Beijing 100098,China);Study on Erect Column in Deep Foundation Pit Engineering in Soft Soil Area[J];施工技术;2007-01
2 Xu Jianjun~1 Liu Aihua~2(1. Nanjing Metro Co., Ltd. , Nanjing 210008; 2. Beijing Urban Engineering Design and Research Institute, Co. , Ltd. , Beijing 100037);Design and Research on the Structure of Joints between Beams and Columns of Sanshanjie Station in Nanjing Metro[J];都市快轨交通;2006-05
3 ZHAO Qi~1,XIE Jian-bin~1,MAO Zhen-wei~1(1.Shanghai NO.2 Construction Corporation,Shanghai 200080,P.R.China);Design and Construction of the Joint Node Used in the Deep Foundation by Topdown Construction Method[J];地下空间与工程学报;2006-04
4 Dai Biaobing Fan Qingguo Zhao Xihong(Department of Geotechnical Engineering,Tongji University Shanghai 200092);A STUDY ON MONITORING OF UP-DOWN CONSTRUCTION FOR DEEP EXCAVATION ENGINEERING[J];工业建筑;2005-09
5 DENG Wen-long (Shanghai NO.2 Construction Co.Ltd, Shanghai 200080, China);The Top-down Construction Technique for Super Foundation of Changfeng Building[J];地下空间与工程学报;2005-04
6 CHEN Pei-tai (Shanghai Tunnel Engineering & Rail Transit Design and Research Institute, Shanghai 200070, China);Discussion on the Key Techniques of Top-down Method in Soft Soil and Its Effects on the Surrounding[J];地下空间与工程学报;2005-04
7 WANG Mei-hua, JI Fang (Shanghai No.7 Construction Co.Ltd, Shanghai 200050, China);Discussion on the Construction Techniques of Oversized Excavation Pit Constructed by Top-down Method[J];地下空间与工程学报;2005-04
8 LUO Wen(Lianyungang Municipal Construction Engineering Quality Supervision Station);Reverse Construction Method of Basement Structures[J];工程质量;2004-12
9 Wu Xian;Measurement and Analysis of Reserved Construction Method for Extra Large Basement in Shanghai Chang Feng Commercial Mart[J];建筑施工;2004-04
10 Jiang Shu Jie;Application and Prospective Review on Reserved Construction Method for Urban Underground Space Development[J];建筑施工;2004-04
©2006 Tsinghua Tongfang Knowledge Network Technology Co., Ltd.(Beijing)(TTKN) All rights reserved