《Value Engineering》 2011-02
Add to Favorite Get Latest Update

Analysis of Water Storage Time for Power Generation Ahead of Schedule in Huanghuazhai Reservoir

Du Jing;Li Guangning(China Power Wafar International Engineering Consulting co.,Ltd.,Beijing 100013,China)  
The Huanghuazhai reservoir will start running for water storage by closing diversion tunnel on 1 November,2010 and generating power on 1 January,2011 according to the schedule.The power station is possible to generate power ahead of planning under the consideration of speeding up of construction and other advantageous factors.Time for closing gate and storing water is suggested in late September or early October,2010 after analysis of the influence of ahead of schedule of closing gate for power generation and early stage of water storage on the pressure resistant ability of the gate and the overtopping risk in September and October,2010 when the scheduled date is moved up to the period.
【CateGory Index】: TV737
Download(CAJ format) Download(PDF format)
CAJViewer7.0 supports all the CNKI file formats; AdobeReader only supports the PDF format.
【Citations】
Chinese Journal Full-text Database 3 Hits
1 LI Wei, GUO Shenglian, YI Songsong, LIU Pan (Wuhan University, Wuhan 430072, China);Analysis of Initial Impounding Time for Shuibuya Reservoir[J];Hydropower Automation and Dam Monitoring;2006-04
2 An Xindai, Wang Yufeng, Li Fusheng (Institute of Reconnaissance, Design, Planning and Research, YRCC, Zhengzhou,450003)(35) Xiaolangdi reservoir will start running for water storage by closing diversion tunnel no.2 and no.3 on 1 November,19;Analysis of Water Storage Time for Power Generation Ahead of Schedule in Xiaolangdi Reservoir[J];YELLOW RIVER;1999-01
3 Zhang Guoqing Xiao Lin Zhao Yinglin (Wuhan University of Hydraulic and Electric Engineering);THE CALCULATION AND SCHEME SELECTION OF BEGINNING PERIOD STORAGE OF RESERVOIR FOR HYDROPOWER[J];Water Resources and Power;1992-04
【Co-citations】
Chinese Journal Full-text Database 6 Hits
1 LI Wei, GUO Shenglian, YI Songsong, LIU Pan (Wuhan University, Wuhan 430072, China);Analysis of Initial Impounding Time for Shuibuya Reservoir[J];Hydropower Automation and Dam Monitoring;2006-04
2 LI Xi can 1,ZHANG Wei 1,SONG Yan 2 (1.Shangdong Hydraulic Engineering College,Taian 271000,Shandong; 2.Taian Hydraulogy and Water Resources Office,Taian 271000,Shandong);The Pattern of Multi decision Making for Multistage and Multiobjective System[J];FUZZY SYSTEMS AND MATHEMATICS;1999-03
3 FENG Yu(Chengdu Hydropower Investigation and Design Inst.,CHECC,Chengdu 610072,China);Analysis on the Process of Impounding Water and Power Generation Quantity About an Ahead of Schedule Impounding Scheme of Mao' ergai Hydropower Station[J];Journal of Sichuan University(Engineering Science Edition);2010-S1
4 Chen Shouyu Dalian university of technology, Dalian, 116024;FUZZY CONCEPT QUANTIFICATION THEORY AND ITS APPLICATION[J];Water Resources and Power;1993-04
5 WU Ping,ZHANG Jin-xin(College of Water Conservency and Hydropower Engineering,Hohai University,Nanjing,210098,China);Fuzzy Decision-making Technique Used in Selecting Reservoir Filling Scheme in the Early Stage[J];Water Conservancy Science and Technology and Economy;2007-08
6 Zhao Qin1,He Jiangda2,Liang Zhaojiang2 (1 General Ecological Environment Monitoring Station of Soil and Water Conservation of Sichuan Province, Chengdu 610041 China) (2 College of Hydraulic Engineering,Sichuan University, Chengdu 610065 China);MODIFICATION TO CONVENTIONAL DESIGN METHOD OF PLUG FOR DIVERSION TUNNEL[J];Chinese Journal of Rock Mechanics and Engineering;2004-08
【Secondary Citations】
Chinese Journal Full-text Database 4 Hits
1 An Xindai, Wang Yufeng, Li Fusheng (Institute of Reconnaissance, Design, Planning and Research, YRCC, Zhengzhou,450003)(35) Xiaolangdi reservoir will start running for water storage by closing diversion tunnel no.2 and no.3 on 1 November,19;Analysis of Water Storage Time for Power Generation Ahead of Schedule in Xiaolangdi Reservoir[J];YELLOW RIVER;1999-01
2 Zhang Guoqing Xiao Lin Zhao Yinglin (Wuhan University of Hydraulic and Electric Engineering);THE CALCULATION AND SCHEME SELECTION OF BEGINNING PERIOD STORAGE OF RESERVOIR FOR HYDROPOWER[J];Water Resources and Power;1992-04
3 LIU Yu, WANG Yu-hua,ZHOU Bao-hong (China Yangtze Power Stock Company, Yichang Hubei 443002);The cascade reservoir dispatching system and its application to the initial impoundment of Three Gorges Reservoir[J];Water Power;2003-12
4 LIU Pan, GUO Sheng-lian, WANG Cai-jun, ZHOU Fen (Wuhan University, Wuhan430072, China);Optimization of limited water level in flood season and impounding scheme for reservoir in Three Gorges Project[J];Journal of Hydraulic Engineering;2004-07
©2006 Tsinghua Tongfang Knowledge Network Technology Co., Ltd.(Beijing)(TTKN) All rights reserved