Analysis on the Process of Impounding Water and Power Generation Quantity About an Ahead of Schedule Impounding Scheme of Mao' ergai Hydropower Station

FENG Yu(Chengdu Hydropower Investigation and Design Inst.,CHECC,Chengdu 610072,China)  
The power generation benefit of hydropower station will increase when an ahead of schedule impounding scheme is carried out.The influence on initial impounding process of Mao’ergai Hydropower Station was analyzed combing with reservoir runoff,downstream water requirements,impounded water level and level rising rate.The power generations of the original scheme and an ahead of schedule impounding scheme were calculated during De-cember 2011 to April 2012.The power generations which were generated by Mao’ergai,Se’ergu and Liuping hy-dropower stations in two conditions showed that the power generation of all the hydropower stations was increased with the ahead of schedule impounding scheme,and more economic benefits can be created in the new impounding scheme of Mao’ergai Hydropower Station.According to the comparison of generated energy during December 2011 to April 2012 between the original scheme and impounding program in advance,the generated energy results of Mao’ergai,Se’ergu and Liuping hydropower stations in two conditions can be achieved respectively.The results showed that the generated energy of these stations is increased by impounding in advance.
【CateGory Index】: TV737
Download(CAJ format) Download(PDF format)
CAJViewer7.0 supports all the CNKI file formats; AdobeReader only supports the PDF format.
【Citations】
Chinese Journal Full-text Database 5 Hits
1 LI Wei, GUO Shenglian, YI Songsong, LIU Pan (Wuhan University, Wuhan 430072, China);Analysis of Initial Impounding Time for Shuibuya Reservoir[J];Hydropower Automation and Dam Monitoring;2006-04
2 An Xindai, Wang Yufeng, Li Fusheng (Institute of Reconnaissance, Design, Planning and Research, YRCC, Zhengzhou,450003)(35) Xiaolangdi reservoir will start running for water storage by closing diversion tunnel no.2 and no.3 on 1 November,19;Analysis of Water Storage Time for Power Generation Ahead of Schedule in Xiaolangdi Reservoir[J];YELLOW RIVER;1999-01
3 Zhang Guoqing Xiao Lin Zhao Yinglin (Wuhan University of Hydraulic and Electric Engineering);THE CALCULATION AND SCHEME SELECTION OF BEGINNING PERIOD STORAGE OF RESERVOIR FOR HYDROPOWER[J];Water Resources and Power;1992-04
4 Peng Yang\ Li Yitian\ Xie Baoling\ Zhao Mingdeng (Wuhan University Key Lab. of the Water and Sediment Sciences of Ministry of Education, Wuhan\ 430072);Study on an ahead of schedule impouding scheme of the Three Gorges Project (TGP) in the flood recession period[J];Journal of Hydroelectric Engineering;2002-03
5 GAO Lin-zhang WU San-gui WANG Xiao-e (Dadu River Basin Hydropower Development Corporation,SPC,Chengdu,Sichuan,610044,China);Basic Theory of Early Power Generation Benefit Analysis of Hydropower Project[J];Sichuan Water Power;2008-04
【Co-citations】
Chinese Journal Full-text Database 10 Hits
1 LI Wei, GUO Shenglian, YI Songsong, LIU Pan (Wuhan University, Wuhan 430072, China);Analysis of Initial Impounding Time for Shuibuya Reservoir[J];Hydropower Automation and Dam Monitoring;2006-04
2 DENG Jin-yun1,XU Fang2,CHEN Jian1,GAN Fu-wan1 (1.Key Laboratory of Water Resource and Hydropower Engineering Sciences,Wuhan University,Whuan 430072,China;2.River &Ocean Engineering Department,Chongqing Jiaotong University,Chongqing 400074,China);Study on the Control Water Level of Three Gorges Reservoir in September Considering the Impact of Sediment Deposition[J];Port Engineering Technology;2007-02
3 LI Yitian,DENG Jinyun,GAN Fuwan State Key Laboratory of Water Resources and Hydropower Engineering Science,Wuhan University,Wuhan 430072,China;Opportunity, Challenge and Our Strategy in Navigable Channel Constructions in the Yangtze River[J];Science & Technology Review;2007-03
4 LI Xi can 1,ZHANG Wei 1,SONG Yan 2 (1.Shangdong Hydraulic Engineering College,Taian 271000,Shandong; 2.Taian Hydraulogy and Water Resources Office,Taian 271000,Shandong);The Pattern of Multi decision Making for Multistage and Multiobjective System[J];FUZZY SYSTEMS AND MATHEMATICS;1999-03
5 Chen Shouyu Dalian university of technology, Dalian, 116024;FUZZY CONCEPT QUANTIFICATION THEORY AND ITS APPLICATION[J];Water Resources and Power;1993-04
6 LI Yitian,GAN Fuwan,DENG Jinyun(State Key Laboratory of Water Resources and Hydropower Engineering,Wuhan University,Wuhan 430072);Preliminary study on impounding water of Three Gorges Project in September[J];Journal of Hydroelectric Engineering;2006-01
7 DENG Jinyun,LI Yitian,CHEN Jian,GAN Fuwan(State Key Laboratory of Water Resource and Hydropower Engineering Sciences,Wuhan University,Whuan 430072);Study on the controlled water levels of Three Gorges Reservoir in September with considering the impact of sediment deposition[J];Journal of Hydroelectric Engineering;2008-03
8 LI Yitian,GAN Fuwan,DENG Jinyun,CHEN Jian(State Key Laboratory of Water Resources and Hydropower Engineering Science,Wuhan University,Wuhan 430072);Preliminary Study on Optimization of the regulation of flood controlled water level of Three Gorges Project[J];Journal of Hydroelectric Engineering;2008-04
9 DENG Jin-yun(State Key Laboratory of Water Resources and Hydropower Engineering Science,Wuhan University,Wuhan 430072,China);Analysis on the Discharge Change at Yichang of Impounding Water ahead of Schedule of the Three Gorges Reservoir[J];Water Conservancy Science and Technology and Economy;2006-12
10 WU Ping,ZHANG Jin-xin(College of Water Conservency and Hydropower Engineering,Hohai University,Nanjing,210098,China);Fuzzy Decision-making Technique Used in Selecting Reservoir Filling Scheme in the Early Stage[J];Water Conservancy Science and Technology and Economy;2007-08
【Secondary Citations】
Chinese Journal Full-text Database 7 Hits
1 Li Yitan (Wuhan University of Hydraulic and Electric Engineering) Shang Quanmin (The Office of State Flood Control & Drought Relief Headquarters);Modeling of sediment transport in unsteady flow[J];JOURNAL OF SEDIMENT RESEARCH;1998-01
2 An Xindai, Wang Yufeng, Li Fusheng (Institute of Reconnaissance, Design, Planning and Research, YRCC, Zhengzhou,450003)(35) Xiaolangdi reservoir will start running for water storage by closing diversion tunnel no.2 and no.3 on 1 November,19;Analysis of Water Storage Time for Power Generation Ahead of Schedule in Xiaolangdi Reservoir[J];YELLOW RIVER;1999-01
3 Zhang Guoqing Xiao Lin Zhao Yinglin (Wuhan University of Hydraulic and Electric Engineering);THE CALCULATION AND SCHEME SELECTION OF BEGINNING PERIOD STORAGE OF RESERVOIR FOR HYDROPOWER[J];Water Resources and Power;1992-04
4 LIU Yu, WANG Yu-hua,ZHOU Bao-hong (China Yangtze Power Stock Company, Yichang Hubei 443002);The cascade reservoir dispatching system and its application to the initial impoundment of Three Gorges Reservoir[J];Water Power;2003-12
5 ZHOU Jian\|jun 1, LIN Bing\|nan 2, ZHANG Ren 1 (1 Tsinghua University, Beijing\ 100084, China; 2 China Institute of Water Resources and Hydropower Research, Beijing\ 100044, China);An optimized operation scheme for reducing deposition and enhancing flood control capacity of the Three Gorges Project Reservoir[J];JOURNAL OF HYDRAULIC ENGINEERING;2000-10
6 ZHOU Jian\|jun 1, LIN Bing\|nan 2, ZHANG Ren 1 (1.Tsinghua University, Beijing\ 100084, China; 2.China Institute of Water Resources and Hydropower Research, Beijing\ 100044, China);Optimized operation scheme for deposition reduction and enhancement flood control capacity of Three Gorges Project reservoir[J];Journal of Hydraulic Engineering;2002-03
7 LIU Pan, GUO Sheng-lian, WANG Cai-jun, ZHOU Fen (Wuhan University, Wuhan430072, China);Optimization of limited water level in flood season and impounding scheme for reservoir in Three Gorges Project[J];Journal of Hydraulic Engineering;2004-07
©2006 Tsinghua Tongfang Knowledge Network Technology Co., Ltd.(Beijing)(TTKN) All rights reserved