Guangzhou Port Hongshengsha Wharf Strengthening and Repair with Carbon Fibre

CHEN Xian-rong(Guangdong Hangsheng Construction Group Co.,Ltd.,Guangzhou 511442,China)  
After 20 years′ operation,some failures occurred in members and facilities of Guangzhou Port Hongshengsha Wharf.Twentyone of the 80 pile caps checked were found damaged in different degrees,among which,cracks in 4 pile caps were developing deformation.According to design requirement,carbon fibre strengthening technique and epoxy cement mortar technique are adopted to repair and strengthening the pile caps.
【CateGory Index】: U656.1