Study on Depth Effect and Critical Pile Length of Belled Pile

Zhang Lei1,2,Gao Guangyun2(1.Shanghai Shenyuan Geotechnical Co.,Ltd,Shanghai 200092,China;2.Key Laboratory of Geotechnical and Underground Engineering of Ministry of Education,Tongji University,Shanghai 200092,China)  
The purpose to study the depth effect of the pile is to get appropriate technical and economic indicators.The belled pile has always been considered as a large diameter pile,but the deformation behavior and failure state of belled piles are similar to and different from those of equal diameter piles,because of their enlarged tip.The method to study the depth effect was suitable for large diameter pile,but not for belled pile.Based on the characteristics of belled pile,the depth effect was studied with considering the influence of pile length to the end resistance.In this paper the influence of pile length on technical and economic indexes of belled pile with the numerical method was analyzed,and a total of 95 large-diameter belled pile tests in area of Hefei city were studied.The statistical results were analyzed,the relationship of the end resistance distribution proportion and the pile length was obtained,and the suggested value of critical design length of belled pile was proposed in the paper.Finally,the suggested value for the length of belled pile will be further verified independently with the results of a group of additional belled pile tests.
【CateGory Index】: TU473.1
Download(CAJ format) Download(PDF format)
CAJViewer7.0 supports all the CNKI file formats; AdobeReader only supports the PDF format.
【Citations】
Chinese Journal Full-text Database 8 Hits
1 Gao Guangyun et al.;Vertical Bearing Behaviour of Manually Excavated Belled Pile[J];Geotichnical Investigation and Surveying;2002-01
2 ZHANG Lei1,GAO Guangyun1,GAO Meng1,2,GU Baohe3(1.Key Laboratory of Geotechnical and Underground Engineering of Education of Ministry,Tongji Univesity,Shanghai 200092,China;2.Shandong Province key Laboratory of Civil Engineering & Disaster Prevention andMitigation,Shandong University of Science and Technology,Qingdao 266510,China;3.China Institute of Geotechnical Investigation and Surveying,Beijing 100007,China);A method of determining the deformation modulus of large diameter belled pile[J];Journal of Building Structures;2010-S2
3 JIANG Jian - ping 1 ,GAO Guang - yun 1 ,WANG Ming - wu 2 (1.Department of Geotechnical Engineering,Tongji University,Shanghai200092,China;2.Institute of Architecture Engineering,Hefei University of Technology,Hefei230009,China)[;FEM Numerical Simulation on Effective Length of Large Diameter and Super-long Pile[J];Building Science;2003-03
4 ZHANG Zhi yong, CHEN Xiao ping (College of Civil and Architectural Engineering, Wuhan Univ. of Hydr. & Elec. Eng., Wuhan 430072, China);Numerical simulation of critical length of belled single pile[J];JOURNAL OF WUHAN UNIVERSITY OF HYDRAULIC AND ELECTRIC ENGINEERING;2000-03
5 GAO Guang-yun1,JIANG Jian-ping2,GU Bao-he3 (1. Department of Geotechnical Engineering,Tongji University,Shanghai 200092,China; 2. College of Traffic Transportation,Shanghai Maritime University,Shanghai 200135,China; 3. Comprehensive Institute of Geotechnical Investigation and Surveying,Ministry of Construction,Beijing 100007,China);COMPARATIVE STUDY ON BELLED AND EQUAL-DIAMETER PILES[J];Chinese Journal of Rock Mechanics and Engineering;2005-03
6 DENG Hong -liang (The solid mechanics research center,Beijing University of Aeronautics and Astronauts,Beijing100083,China);Numerical solution of depth effect and determination method of bearing capacity for pile with expanded end[J];Rock and Soil Mechanics;2002-01
7 ZENG You-jin,ZHANG Wei-min,WANG Nian-xiang,XU Guang-ming (Nanjing Hydraulic Research Institute, Nanjing 210024, China);Discussion of several problems about effective length of foundation pile[J];Rock and Soil Mechanics;2003-S2
8 GAO Guang-yun1,JIANG Jian-ping1,Gu Bao-he2 (1. Department of Geotechnical Engineering, Tongji University, Shanghai 200092, China; 2. Comprehensive Institute of Geotechnical Investigation and Design, Ministry of Construction, Beijing 100007, China);Vertical bearing behavior of large diameter short-belled pier in sand-cobble layer[J];Rock and Soil Mechanics;2004-03
【Co-citations】
Chinese Journal Full-text Database 10 Hits
1 GAO Guang yun et al;Determination of Vertical Bearing Capacity of Large Diameter Belled Pile by Two Static Load Methods[J];Underground Space;2003-03
2 ZHANG Dong-liang,YANG Long-cai,WANG Bing-long(Key Laboratory for Highway and Traffic Engineering of Ministry of Education,Tongji University,Shanghai 200331,P.R.China);Experimental Analysis and Calculation of the Up-lift Resistance Bearing Capacity of Bored Cast-in-place Pile with Enlarged Bottom[J];Chinese Journal of Underground Space and Engineering;2006-05
3 GAO Guang-yun1,GUO Xing-yu1,FENG Shi-jin1,LOU Rong-xiang2(1.Department of Geotechnical Engineering,Tongji University,Shanghai 200092,China;2.Shanghai Guanglian Construction Development Co.Ltd,Shanghai 200438,China);Numerical Simulation of Vertical Bearing Behavior of Belled Pier Ended on the Coarse Sand[J];Chinese Journal of Underground Space and Engineering;2007-02
4 FENG Shi-jin1,2,GAO Guang-yun1,2,GUO Xing-yu1,2(1.Department of Geotechnical Engineering,Tongji University,Shanghai 200092,China;2.Key Laboratory of Geotechnical and Underground Engineering of Ministry of Education,Tongji University,Shanghai 200092,China);Effect of Dimensional Variation on Vertical Bearing Behavior of Large Diameter Belled Pier[J];Chinese Journal of Underground Space and Engineering;2008-05
5 Wang Cheng,Chen Xiayu (Department of Tunnel and Geotechnical Engineering,Chongqing Jiaotong University,Chongqing 400074,China);Study of Effective Length of Piles Based on Parabolic Frictional Resistance[J];Chinese Journal of Underground Space and Engineering;2011-03
6 Peng Baixing,Wang Xinghua;Research on the Baring of Large Diameter Belled Pile in Sandy Cobble Layer[J];Urban Geotechnical Investigation & Surveying;2006-01
7 QIN Li1,WANG Li-huan1,CHEN Bing-jun2,CHEN Hao3 (1.Architecture Engineering College,Northeast Dianli University,Jilin Jilin 132012;2.Changchun Power Supply Company,Jilin Changchun 130041;3.Tenth Engineering Corps of China Airport Construction,Hebei Baoding 071051);Numerical simulation of vertical bearing for single borehole cast-in-place concrete pile[J];Journal of Northeast Dianli University;2011-Z1
8 CHEN Rong1,2,HAO Dong-xue1,FAN Guang-sen1(1.Architecture Engineering College,Northeast Dianli University,Jilin Jilin 132012;2.Institute of Geotechnical Engineering,Dalian University of Technology,Dalian 116085);FE Analysis of Uplift Capacity of Pedestal Pile based on ALE Method[J];Journal of Northeast Dianli University;2011-Z1
9 Ruan Xiang1,2 Gao Guangyun1(1Department of Geotechnical Engineering,Tongji University,Shanghai 200092,China) (2Shenzhen Gongkan Geotechnical Engineering Co.,Ltd.,Shenzhen 518026,China);Analytical solution and test analysis of vertical tip bearing capacity of large diameter belled pile[J];Journal of Southeast University(Natural Science Edition);2009-S2
10 DENG Hong-liang The Civil Engineering College, Beijing University of Technology, Beijing, 100022;STUDY OF COEFFICIENTS MODIFYING AREA OF END OF PILE WITH LARGE DIAMETERle ACTED ON BY END-PILE RESISTANCE[J];Earth and Environment;2005-S1
China Proceedings of conference Full-text Database 4 Hits
1 PEI Mengde~①SHI Zhenming~(①②) LIU Weitao~①SONG Shuang~③(①Department of Geotechnical Engineering,Tongji University,Shanghai 200092 ) (②Key Laboratory of Geotechnical and Underground Engineering of Ministry of Education,Tongji University,Shanghai 200092) (③Shanghai Tongji Construction Quality Inspection Station,Shanghai 200092 );COMPARATIVE IN-SITU EXPERIMENT STUDY ON PEDESTAL AND NORMAL PILES OF A SET IN SOFT SOILS[A];[C];2008
2 DENG Hong-liang (The Civil Engineering College,Beijing University of Technology,Beijing,100022);STUDY OF COEFFICIENTS MODIFYING AREA OF END OF PILE WITH LARGE DIAMETERle ACTED ON BY END-PILE RESISTANCE[A];[C];2005
3 DENG Hong-liang, XIE Xiang-wen, GUO Yu-song ( College of Architecture and Civil Engineering, Beijing University of Technology, Beijing 100022, China; Physical Prospect Team, Yellow River Conservancy Committee, Zhengzhou 450000, China);STUDY ON LOAD TRANSFER AND DETERMINATION METHOD OF BEARING CAPACITY FOR ENLARGED PILE[A];[C];2005
4 ZHAO Jian-bin , WANG Zhi-bin , SHI Yong-qiang (Shenyang Jianzhu University, 110168, China);NUMERICAL SIMULATION ANALYSIS ON EFFICIENCY OF STATIC PRESSED PHC PIPE PILE GROUP[A];[C];2013
【Secondary Citations】
Chinese Journal Full-text Database 10 Hits
1 GAO Guang yun et al;Determination of Vertical Bearing Capacity of Large Diameter Belled Pile by Two Static Load Methods[J];Underground Space;2003-03
2 Zhang Mangqing You Weihu Yu Zhaorong Luo Zhanyu Zheng Yitong (Fujian Geo construction Group Co.,Shanghai,200125);Discussion on the Operational Technique of Super length Piles in the Soft Foundation in Shanghai[J];GEOLOGY OF FUJIAN;1999-01
3 ;深层平板静力载荷试验测定土的变形模量[J];GEOTICHNICAL INVESTIGATION AND SURVEYING;2000-04
4 Gao Guangyun et al.;Vertical Bearing Behaviour of Manually Excavated Belled Pile[J];Geotichnical Investigation and Surveying;2002-01
5 Jiang Jianping et al.;Behavior of Load Transfer of Large Diameter Belled Pier in Sandy Cobble Layer[J];Geotechnical Investigation and Surveying;2003-05
6 Zhang Rongxiang et al.;Analysis on Bearing Capacity of Large Diameter Belled Pile and Settlement Deformation[J];GEOTICHNICAL INVESTIGATION AND SURVEYING;1998-04
7 He Kaisheng Yuan Wenming(Nanjing Hydraulic Research Institute Nanjing 210024);BEARING CAPACITY AND CRITICAL LENGTH OF SUPER LONG CEMENT-MIXING PILE[J];INDUSTRIAL CONSTRUCTION;2000-01
8 Chi Yuejun(Tsinghua University\ Beijing\ 100084) Gu Xiaolu(Tianjin University\ Tianjin\ 300072)Zhou Sisi\ Sun Junling(3rd Design & Survey Institute, M.R.\ Tianjin\ 300142)\ Zhang Jianyu(Architecture Design Institute,M.C.\ Beijing\ 100044);EXPERIMENTAL RESEARCH ON BEARING BEHAVIOR OF LARGE DIAMETER AND SUPER\|LONG BORED PILES[J];INDUSTRIAL CONSTRUCTION;2000-08
9 Shu Xiang\ Huang Yu(Department of Geotechnical Engineering, Tongji University\ Shanghai\ 200092);DETERMINING METHOD FOR EFFECTIVE LENGTH OF FOUNDATION PILE[J];Industrial Construction;2001-01
10 Gao Guanyun(Fourth Design and Research Institute,Ministry of Machine-Building Industry 471039);CALCULATION AND MEASUREMENT OF SETTLEMENT FOR BELLED PIER BASE IN LOESS[J];;1995-01
©2006 Tsinghua Tongfang Knowledge Network Technology Co., Ltd.(Beijing)(TTKN) All rights reserved