Risk Control in Slurry Shield Break-through Construction of River Crossing Tunnels

Fang Jun(AECOM Consultants(Shenzhen) Pte.Ltd.Shanghai Office,Shanghai 200040,China)  
Recently,slurry shield has been often adopted in the construction of river crossing tunnels in Shanghai,through which rich engineering experience has been gained in this particular area.The Qingchaosha Water Transport Tunnels Crossing Yangtze River has been taken as the background project,in which two slurry tunnel boring machines of Φ7075mm in diameter were used,and continuous tunnel boring over 7.17 km has been achieved.Major engineering difficulties,including alignment control,stabilization for excavation face and sealed/impermeable control for shield tail,have been encountered and dealt with during the break through of the shield.In view of the importance and risks of the break-through of shield,the current paper is to focus on the related preparation work and risk control measures during the construction of TBM break-through from the perspective of risk control,in which the application of such methods including vertical jack-up for survey positioning system,breaking through under water and cutting off shield tail were proved to be successful.The relevant experience could be a good example to other TBM constructions.
【CateGory Index】: U455.43
Download(CAJ format) Download(PDF format)
CAJViewer7.0 supports all the CNKI file formats; AdobeReader only supports the PDF format.
【Citations】
Chinese Journal Full-text Database 7 Hits
1 LI Gang1,HUANG Hong-wei1(Department of Geotechnical Engineering,College of Civil Engineering,Tongji University,Shanghai 200092,P.R.China);Risk Analysis on Arriving into Shaft of Super Large Diameter Shield Machine under Water[J];Chinese Journal of Underground Space and Engineering;2009-S1
2 Gu Yun Fang Jun;Shield Construction Risk Evaluation of Shanghai Qingcaosha Raw Water River Crossing Tunnel[J];Underground Engineering and Tunnels;2009-01
3 Ling Yufeng,Guo Hao,Li Muhan;Shield Break-in in Water Construction Technology of Shanghai Yangtze River Tunnel Construction[J];Underground Engineering and Tunnels;2010-02
4 Zhang Liankai;Technique of Shield Tunneling into Shaft in Water for Qingcaosha Crossing-river Pipe Tunnel[J];Urban Roads Bridges & Flood Control;2010-07
5 ZHANG Bin(China Railway Erju Co.,Ltd.,Chengdu 610031,China);Construction Technology of Launching and Arriving for Shield Tunnelling in Complex Geology[J];Tunnel Construction;2009-03
6 Bai Yun1 Tang Jing2(1.Shanghai Urban Construction Group,Shanghai 200023,China )(2.Tongji University,Shanghai 200092,China );Experience and lessons from underground construction in Shanghai[J];China Civil Engineering Journal;2007-05
7 Ji Jun(Shanghai Qingcaosha Investment Construction & Development Co.,Shanghai 201913);Waterproofing Design and Implementation Techniques for a Deep Water-conveyance Tunnel and its Joint with the Launching Shaft[J];Modern Tunnelling Technology;2011-04
【Co-citations】
Chinese Journal Full-text Database 10 Hits
1 Yang Zisong1,2,Peng Fangle1,Tan Yong1,Zhang Zeng2(1.Department of Geotechnical Engineering,Tongji University,Shanghai 200092,China; 2.Technical Center,Shanghai Construction(Group) General Co.,Shanghai 200083,China);Analysis of Ventilation Shaft Construction Technology in Soft Soils with "Hanging and Top-Down Method"[J];Chinese Journal of Underground Space and Engineering;2011-01
2 SUN Chuang1,ZHOU Xing-wang2,HAN Yu-fu2 (1.Institute of Civil Engineering and Transportation,Liaoning Technical University,Fuxin Liaoning 123000,China;2.Beijing Coal Mining Engineering Company Ltd.,Beijing 100013,China);Partial Freezing Method Applied in the Restoration of Damaged Subway Tunnels[J];Journal of Yangtze River Scientific Research Institute;2011-08
3 LIU Ling-yun1,YANG De-lei1,2,GUO Hai-zhu3 (1.Department of Building Engineering,Huanghuai University,Henan Zhumadian 463000,China;2.School of Civil Engineering,Tongji University,Shanghai 200092,China;3.Shenzhen Metro Ltd.,Guangdong Shenzhen 518026,China);RISK ANALYSIS OF TUNNEL SHIELD MACHINE DRIVING-IN AND DRIVING-OUT CONSTRUCTION PROCESS IN TUNNELLING ENGINEERING[J];Low Temperature Architecture Technology;2010-08
4 ;三维GIS技术在城市地下空间规划中的应用分析[J];Geotechnical Investigation & Surveying;2008-S1
5 Zhang Boyang(CCCC Tunnel Engineering Co.,Ltd.Beijing 100088,China);The Key Technology of Super Large Diameter Shield Tunnel[J];Chinese Journal of Underground Space and Engineering;2013-03
6 Wu Huaina1,Shen Shuilong1,Ma Yuhong2,Liu Yanbin2,Du Shouji1(1.Department of Civil Engineering,Shanghai Jiaotong University and State Key Laboratory of Ocean Engineering,Shanghai 200240,China;2.Shanghai Huangpu Infrastructure Investment Construction and Development Co.Ltd.,Shanghai 200080,China);Investigation and Analysis on the Leakage of the River-crossing Tunnels in Shanghai[J];Chinese Journal of Underground Space and Engineering;2013-03
7 ZHANG Hongwei,RONG Liang(China Railway Tunnel Stock Co.,Ltd.,Zhengzhou 450000,China);Shield Tunneling through Intermediate Ventilation Shaft on Small-radius Curve with Deep Overburden[J];Tunnel Construction;2012-01
8 ;Construction Technical Measures for Arrival of Shield Machine to Complicated Condition[J];Building Construction;2012-03
9 YANG Zhigang(China Railway South Investment & Development Limited Company,Shengzhen 518000,Guangdong,China);Pre-treatment of Bedrock and Boulders before Shield Boring[J];Tunnel Construction;2012-04
10 WANG Qing LIU Wei-cheng GAO Jun-qiang (Nanjing University of Technology Institute of Surveying and Mapping,Nanjing 210009,China);On construction technique of shield tunnel at sandy soil stratum[J];Shanxi Architecture;2012-30
China Proceedings of conference Full-text Database 2 Hits
1 Jingshun QIAO~1 DeleiYANG~1 Huawei LIU~1 Haizhu GUO~2 Lingyun LIU~1 Zhigang JIA~1 1 Department of Building Engineering,Huanghuai University,Zhumadian 463000,China 2 Shenzhen Metro Ltd.,Shenzhen 518026,China;Risk Analysis of Tunnel Shield Machine Driving-in and Driving-out Construction Process in Zhengzhou Subway Engineering[A];[C];2010
2 Li Chao,Yi Min;Strata Reinforcement Techniques of Shield Tunneling Departure near the Haihe River[A];[C];2011
【Secondary Citations】
Chinese Journal Full-text Database 10 Hits
1 Zhou Wenbo et al.;Construction Technology with Shield and Water-Mud Balance Passing through Freezing Consolidated Area[J];Underground Space;1998-S1
2 BAI Yun~1,TANG Jing~2(1.Shanghai Urban Construction Group,Shanghai 200023,P.R.China;2.Department of Underground Engineering,Tongji University,Shanghai 200092,P.R.China);Risk Management for Underground Project in Soft Soils[J];Chinese Journal of Underground Space and Engineering;2006-01
3 CHEN Long~1,HUANG Hong-wei~2(1.Shanghai Civic Engineering Construction and Developing Ltd., Shanghai 200025;2.The Department of Geotechnical Engineering of Tongji University,Shanghai 200092);Risk Loss Analysis During Construction of Soft Soil Shield Tunnel[J];Chinese Journal of Underground Space and Engineering;2006-01
4 PAN Xue-zheng CHEN Guo-qiang PENG Ming (1.Hangzhou Municipal Bureau of Highway,Hangzhou 310004; 2.Department of Geotechnical Engineering,Tongji University,Shanghai 200092);Risk Assessment on Shield Excavation in Very Large Tunnel Across Qiantang River[J];Chinese Journal of Underground Space and Engineering;2007-S1
5 CHEN Yun,WU Zhu-qing,LIU Jun-jian(School of Traffic and Transportation Engineering,Changsha University of Science & Technology,Changsha 410076,China);Risk evaluation of highway engineering project based on the Fuzzy-AHP[J];Journal of Changsha Communications University;2008-03
6 WEI Liang-wen~(1,2),WU Tao~(1,2),ZHANG Qing-he~(1,2)(1.Department of Geotechnical Engineering,Tongji University,Shanghai 200092,China;2.Geotechnical Key Laboratory,Tongji University,Shanghai 200092,China);STABILITY ANALYSIS OF SOIL BODY OF SHIELD STARTING SHAFT IN LARGE-DIAMETER SHIELD TUNNELING[J];Low Temperature Architecture Technology;2006-02
7 Song Minhua Feng Aijun Wang Xinjie(Beijing Urban Engineering Design and Research Institute Co. , Ltd. , Beijing 100037);Promote Underground Space Development Through Urban Rail Transit[J];Urban Rapin Rail Transit;2005-01
8 BAI Yun1, TANG Jing2, MAO Jian-min3 (1.Shanghai Urban Construction Group, Shanghai 200023; 2. Department of Underground Engineering, Tongji University, Shanghai 200092; 3.Shanghai Y.S Engineering management & consulting Co., Ltd., Shanghai 200000);Application of Risk Management on Metro Line No.10 in Shanghai[J];Tunnel Construction;2007-S2
9 WANG Zu-zhen(Anhui Communications Consulting & Design Institute,Hefei 230031,China);Strengthening Technique with Bonded Rebars in Design and Construction[J];Transport Standardization;2009-21
10 Wang Dong;On the Technology of Shield Construction[J];Friend of Science Amateurs;2006-07
©2006 Tsinghua Tongfang Knowledge Network Technology Co., Ltd.(Beijing)(TTKN) All rights reserved