Safety Monitoring Renovation and Deformation Law Analysis for Gezhouba Third Ship Lock

LIU Zuqiang1,YANG Qiru2,YE Qing3(1.Changjiang Geotechnical Engineering Corporation,Changjiang Institute of Survey,Planning,Design and Research,Wuhan 430010,China;2.Pingdingshan City Shilong District Land Resources Bureau,Pingdingshan 467000,China;3.Changjiang Spatial Information Technology Engineering Corporation,Changjiang Institute of Survey,Planning,Design and Research,Wuhan 430010,China)  
The original safety monitoring equipment of the Gezhouba third ship lock is simple,only focused on the surface of the ship lock,and the monitoring accuracy cannot satisfy the requirement of the specifications.By renovation of the safety monitoring arrangement,through the selection,rating and calibration,installation and observation of the monitoring equipment,and with preliminary analysis for the deformation law of the third ship lock,the purpose of the renovation project is attained,and a foundation is laid for establishing an automatic monitoring system.The observation results by new equipment show that:when the ship lock runs at the full water level,the opening degree of the gate wall is smaller than 2 mm compared with the empty gates;the opening and closing of the left and right vertical joints of the lock chamber,the floor and base surface-connected location is less than 0.1 mm.The ship lock deformation is in good correspondence with the water level of the lock chamber and temperature change,in line with general deformation laws of hydraulic structures.
【CateGory Index】: U641.7
Download(CAJ format) Download(PDF format)
CAJViewer7.0 supports all the CNKI file formats; AdobeReader only supports the PDF format.
【References】
Chinese Journal Full-text Database 1 Hits
1 MIAO Changqing;SHI Changhua;WANG Yichun;College of Civil Engineering,Southeast University;Key Laboratory of Concrete and Prestressed Concrete Structure of Ministry of Education;;Research on Structural Safety Monitoring and Evaluation System of the Single Ship Lock in Inland Channel[J];Journal of Wuhan University of Technology(Transportation Science & Engineering);2013-06
【Citations】
Chinese Journal Full-text Database 3 Hits
1 Shan Yongbiao, Li Zhenfu (Tianjin University, Tianjin 300072, China);DESIGN SCHEME OF REFORM IN DAM SAFETY MONITORING SYSTEM OF LONGYANGXIA HYDROPOWER PLANT[J];Dam Observation and Geotechnical Tests;2002-04
2 LIU Zu-qiang , YANG Hong , LIAO Yong-long (Three Gorges Investigation Research Institute, Changjiang Water Resources Commission, Yichang 443003, China) (Three Gorges University, Yichang 443002, China) (Yangtze River Scientific Research Institute, Wuhan 430010, China);Deformation Analysis for the Permanent Shiplock of Three Gorges Project[J];Dam Observation and Geotechnical Tests;2005-02
3 LI Youmu1,ZHANG Shidong2,KANG Youcheng2,HAN Jianxin2 (1.Shaanxi Electric Power Corporation,Xi'an 710041,China;2.Ankang Hydropower Plant,Ankang 725000,China);Reconstruction of Dam Deformation Monitoring System of Ankang Hydropower Station and Data Analysis[J];Hydropower Automation and Dam Monitoring;2007-03
【Co-citations】
Chinese Journal Full-text Database 10 Hits
1 ZHANGZheng-lu,DENG Yong,LUO Chang-lin,LIUZu-qiang,YANG Hong;On Precise Engineering Surveying and Its Application[J];Bulletin of Surveying and Mapping;2006-05
2 LIU Feng-qiu,DONG Jian-ye,SUN Qi-wei,WANG Hai-zhong,ZHANG Shi-zhong,LI Hong(Institute of Crustal Dynamics,China Earthquake Administration,Beijing 100085,China);Development of YZ-CCD Type Automatic Hypsometer and Its Measurement Method[J];Journal of Yangtze River Scientific Research Institute;2008-05
3 YANG Yong (Xin'anjiang Hydropower Plant,Jiande 311608,China);Reform of the First Stage of Automatic Safety Monitoring System for Xin'anjiang Dam[J];Dam Observation and Geotechnical Tests;2005-06
4 LI Ke, CUI Gang (Wuling Power Corporation, Changsha 410004, China) (Nanjing Automation Research Institute, Nanjing 210003, China);Experience in Dam Safety Monitoring Design and Construction[J];Hydropower Automation and Dam Monitoring;2006-04
5 HU Jinlian1, CAO Wan2, LI Tianhe2 (1. Yangtze River Scientific Institute, Wuhan 430010, China) (2. The Second Artillery Command College, Wuhan 430012, China);Stress and Strain Analysis and Prediction for Dam Block 14 of Three Gorges Dam[J];Hydropower Automation and Dam Monitoring;2007-01
6 LI Youmu1,ZHANG Shidong2,KANG Youcheng2,HAN Jianxin2 (1.Shaanxi Electric Power Corporation,Xi'an 710041,China;2.Ankang Hydropower Plant,Ankang 725000,China);Reconstruction of Dam Deformation Monitoring System of Ankang Hydropower Station and Data Analysis[J];Hydropower Automation and Dam Monitoring;2007-03
7 LIU Kang(Chengdu Hydroelectric Investigation & Design Institute of SPC,Chengdu 610072,China);Deformation Monitoring Design and Results Analysis for the Left Bank Steep Slope of Jinping-Ⅰ Hydropower Station[J];Hydropower Automation and Dam Monitoring;2008-03
8 HUANG Huibao1,LU Jiabin1,FENG Jun1,CHEN Hong2(1.Valley Repair & Installation Co.Guodian Dadu River Co.Ltd.,Leshan 614900,China;2.Chengdu Engineering Co.Ltd.of China Light Industry,Chengdu 610015,China);Application and Reform of Corridor Laser Automation Monitoring System of Tongjiezi Hydropower Station[J];Hydropower Automation and Dam Monitoring;2008-05
9 NING De-xing, CHU Cai-ju, GUO Jun and et al. Manwan Hydropower Plant of Huaneng Lancangjiang Hydropower Co., Ltd.;Innovation of the automatic monitoring system of Manwan hydropower station[J];Dam & Safety;2012-02
10 YIN Zheng-guo,MA Yong-fu(Y.R.Wanjiazhai Water Multi-purpose Dam Project Co.,Ltd.,Pianguan County,Shanxi Province 036412);Scheme for Improvement of Dam Safety Monitoring System, Wanjiazhai Water Multi-purpose Dam Project[J];Northwest Hydropower;2012-02
【Co-references】
Chinese Journal Full-text Database 2 Hits
1 Miao Changqing~1 Li Aiqun~1 Han Xiaolin~1 Li Zhaoxia~1 Ji Lin~2 Yang Yudong~2(~1College of Civil Engineering,Southeast University,Nanjing 210096,China)(~2Jiangsu Construction Headquarters of the Yangtse River Bridge,Zhenjiang 212002,China);Monitor strategy for the structural health monitoring system of Runyang Bridge[J];Journal of Southeast University (Natural Science Edition);2005-05
2 CHEN Liang1,MIAO Chang-qing1,2,SONG Hua-li1(1.College of Civil Engineering,Southeast University,Nanjing,Jiangsu 210096, China;2.Key Laboratory of Concrete and Prestressed Concrete Structure of Ministry of Education,Southeast University,Nanjing,Jiangsu 210096,China);Design of Structural Safety Monitoring System for Yangjiawan Ship Lock[J];Journal of Water Resources and Architectural Engineering;2010-05
【Secondary Citations】
Chinese Journal Full-text Database 1 Hits
1 Shan Yongbiao, Li Zhenfu (Tianjin University, Tianjin 300072, China);DESIGN SCHEME OF REFORM IN DAM SAFETY MONITORING SYSTEM OF LONGYANGXIA HYDROPOWER PLANT[J];Dam Observation and Geotechnical Tests;2002-04
©2006 Tsinghua Tongfang Knowledge Network Technology Co., Ltd.(Beijing)(TTKN) All rights reserved