Duration-Cost Optimization Model of Program of South-to-North Water Diversion Project under Restriction of Resources Supplied by Employer

FENG Jing-chun;ZHU Xiao-jing;LI Ming;ZHANG Ke;XUE Song;Hohai University,Business School,Institute of Project Management;Jiangsu Provincial Collaborative Innovation Centre of World Water Valley and Water Ecological Civilization;International River Research Centre;  
Since 2015,the National Development and Reform Commission,the Ministry of Foreign Affairs and the Ministry of Commerce jointly released the VisionandActionsforPromotingtheBuildingofthe BeltandRoadInitiative.Afterwards,more and more large and medium-sized construction projects are undertaken at home and abroad.In order to make sure that the three control objectives of duration,cost and quality can be implemented successfully,the program management of large and medium-sized construction projects came into being.Based on this,this paper focuses on the duration-cost optimization of program,and establishes a time-cost optimization model before the implementation of the program under the condition of resource constraints,then the initial network plan is optimized.After that,taking the penalty fee(f(Ti))into consideration,which is proposed by the employer to the contractor due to the delay of the bidding section on the non-critical path,the duration-cost optimization model during the implementation of the program is constructed,then the optimized network plan before implementation is dynamically adjusted,so that the net present value of the employer's payment can be minimized.Finally,the results of different duration-cost optimization are illustrated by an example:program X of South-toNorth Water Diversion.The results show that the two-stage proposed model can actualize the optimization of program's cost control objective and provide the basis for the employer to determine the starting time of each bidding section in the program.In this way,the program optimization theory can be further improved.
【Fund】: 国家社会科学基金重点资助项目(14AZD024);国家社会科学基金资助项目(17BGL156);国家社会科学基金青年项目(15CJL023)
【CateGory Index】: TV68;TV51
Download(CAJ format) Download(PDF format)
CAJViewer7.0 supports all the CNKI file formats; AdobeReader only supports the PDF format.
【Citations】
Chinese Journal Full-text Database 8 Hits
1 HE Zheng-wen;LIU Ren-jing;HU Xin-bu;School of Management,Xi'an Jiaotong University;;Project scheduling optimization based on interaction between two parties of contracts[J];管理科学学报;2014-08
2 WANG Yi-feng;ZHONG Yi;School of Economic and Management,Xidian University;;Research on Enterprise Program Scheduling Optimization Model Based on the Particle Swarm Algorithm[J];软科学;2014-06
3 ZHANG Chun-sheng;YAN Guang-le;College of Management,University of Shanghai for Science and Technology;;Research on Program Schedule Optimization Based on DSM of Resource Time Factor[J];运筹与管理;2013-04
4 FENG Jing-chun~(1,2),HU Zheng-ren~(1,2),REN Ya-fang~(1,2),WANG Long-bao~(1,2) (1.Business School,Hohai University,Nanjing 210098,China; 2.Research Institute of Project Management Informationization,Hohai University,Nanjing 210098,China);Construction period reward model of contract works for large and medium-sized projects from a viewpoint of program[J];系统工程理论与实践;2012-06
5 HE Zheng-wen,LIU Ren-jing,XU Yu School of Management,Xi'an Jiaotong University,Xi'an 710049,China;Cash flow balanced project scheduling optimization based on different payment conditions[J];管理科学学报;2011-08
6 SU Ju-ning,JIANG Chang-sheng,LIU Chen-guang,CHEN Ju-hong(1.School of Economic and Management,Xi'an University of Tecuaology,Xi'an 710054,China;2.Bestsbet(Hefei)Co.,LTD,Hefei 230011,China);Research on Project Duration Coordination and Optimization of Construction Supply Chain Based on Bonus-Penalty Mechanism[J];中国管理科学;2010-01
7 Liang Laixing,Xiong Yan(School of Business,Central South University,Changsha 410083,China);A R&D cost management model based on lifecycle[J];科研管理;2010-01
8 YIN Yi-lin1,2,LIU Yan-hui1(1.School of Management,Tianjin University,Tianjin 300072;2.School of Management,Tianjin University of Technology,Tianjin 300191);Analysis of Large-scale Construction Projects on Integration Management Pattern Based on Program Governance Framework[J];软科学;2009-08
【Co-citations】
Chinese Journal Full-text Database 10 Hits
1 NING Min-jing;HE Zheng-wen;LIU Ren-jing;School of Management,Xi'an Jiaotong University;;Optimization of Cash Flow Balanced Project Scheduling with Random Duration of Activities Based on Robust Constraint[J];系统工程;2015-09
2 PENG Ben-hong;GU Xiao-fen;WU Bai-yu;;Project Governance Mechanism for Service- oriented Manufacturing in the Transformation and Upgrading of Manufacturing Industry[J];产经评论;2015-05
3 Wang Lin;Yang Jianzheng;Yin Shi;Business School, University of Shanghai for Science and Technology;;The Business Mode of "Internet+Construction"——A Case Study of Wishbuild Company at Shanghai[J];当代经济管理;2015-10
4 WANG Ling;LU Cai-xia;Beijing China Power Information Technology Co. Ltd;;Research and Analysis of Software Ability Objective Research Based on Artificial Cost Budget[J];电脑知识与技术;2014-36
5 TAO Liang-yan;LIU Si-feng;FANG Zhi-geng;WU Li-feng;JIANG Zhi-ping;College of Economics and Management,Nanjing University of Aeronautics and Astronautics;Centre for Computational Intelligence,De Montfort University;;"Super-conflict equalization" game model for complex product development scheduling based on multi-level GERT[J];控制与决策;2014-11
6 GUAN Du-juan;GUO Peng;School of Management,Northwestern Polytechnical University;;Relationship Classification of Project Portfolio Based on the Measurement of Interaction Effects and Their Influences[J];软科学;2014-10
7 HE Zheng-wen;LIU Ren-jing;HU Xin-bu;School of Management,Xi'an Jiaotong University;;Project scheduling optimization based on interaction between two parties of contracts[J];管理科学学报;2014-08
8 LIU Yong;WANG Jian-ping;CUI Cai-yun;School of Civil Engineering and Architecture,Zhejiang Sci-Tech University;Institute of Project Management,China University of Mining and Technology;Department of Civil Engineering,North China Institute of Science and Technology;;Operating Mechanism Design of the Project Integrated Management Mode[J];工程管理学报;2014-03
9 WANG Yi-feng;ZHONG Yi;School of Economic and Management,Xidian University;;Research on Enterprise Program Scheduling Optimization Model Based on the Particle Swarm Algorithm[J];软科学;2014-06
10 MA Zhi-qiang;HE Zheng-wen;HUANG Chang-sheng;School of Management,Xi′an Jiaotong University;The Key Lab of the Ministry of Education for Process Control&Efficiency Engineering;School of Economics and Management,China University of Petroleum;;Cash Flow Balanced Project Scheduling Optimization[J];工业工程与管理;2014-03
【Secondary Citations】
Chinese Journal Full-text Database 10 Hits
1 ZHANG Xianzhe1,FANG Jun2(1.Logistics and Engineering Management School,Hubei University of Economics,Wuhan 430205,China;2.Wuhan University of Technology,Wuhan 430070,China);Improved dynamic programming algorithm for optimization of projects resources management[J];武汉大学学报(工学版);2012-03
2 FENG Jing-chun~(1,2),HU Zheng-ren~(1,2),REN Ya-fang~(1,2),WANG Long-bao~(1,2) (1.Business School,Hohai University,Nanjing 210098,China; 2.Research Institute of Project Management Informationization,Hohai University,Nanjing 210098,China);Construction period reward model of contract works for large and medium-sized projects from a viewpoint of program[J];系统工程理论与实践;2012-06
3 HE Zheng-wen,LIU Ren-jing,XU Yu School of Management,Xi'an Jiaotong University,Xi'an 710049,China;Cash flow balanced project scheduling optimization based on different payment conditions[J];管理科学学报;2011-08
4 LI Jun-ting1,2,WANG Run-xiao1,YANG Yun-tao1 (1.School of Mechatronics,Northwestern Polytechnical University,Xi'an 710072,China; 2.School of Economics and Management,Xi'an Shiyou University,Xi'an 710065,China);Integration scheduling optimization for critical chain multi-project[J];计算机集成制造系统;2011-08
5 HU Xiang-pei,SUN Li-jun,WANG Ya-nan Institute of Systems Engineering,Dalian University of Technology,Dalian 116023,China;A model for disruption management in urban distribution systems[J];管理科学学报;2011-01
6 LI Jian1,2,DA Qing-li2,HE Rui-yin11.College of Engineering,Nanjing Agricultural University,Nanjing 210031,China;2.College of Economics and Management,Southeast University,Nanjing 210096,China;Simultaneous deliveries and pickups[J];管理科学学报;2010-10
7 SU Ju-ning,JIANG Chang-sheng,LIU Chen-guang,CHEN Ju-hong(1.School of Economic and Management,Xi'an University of Tecuaology,Xi'an 710054,China;2.Bestsbet(Hefei)Co.,LTD,Hefei 230011,China);Research on Project Duration Coordination and Optimization of Construction Supply Chain Based on Bonus-Penalty Mechanism[J];中国管理科学;2010-01
8 SHAN Mi-yuan,LIU Yong,REN Bin,ZHANG Ren-long(School of Business Administration,Hunan University,Changsha 410082);Research on Critical Chain Buffer Based on the Perspective of Uncertainties[J];软科学;2009-08
9 REN Shi-ke~1,HE Zheng-wen~2,XU Yu~2(1.School of Management,Lanzhou University,Lanzhou 730000,China;2.School of Management,Xi'an Jiaotong University,Xi'an 710049,China);Study on Bank Credit Limit Based Max-NPV Project Scheduling Problems[J];管理工程学报;2009-02
10 CHAI Guo-rong~1,HONG Zhao-fu~1,HE Zheng-wen~2(1.School of Management,Lanzhou University,Lanzhou 730000,China; 2.Management School,Xi'an Jiaotong University,Xi'an 710049,China);Study on the Bonus-Penalty Structure Optimization of Large-scale Project Based on Flexible Resource-constrained[J];系统管理学报;2009-02
©2006 Tsinghua Tongfang Knowledge Network Technology Co., Ltd.(Beijing)(TTKN) All rights reserved